Реконструкція Костянтинівської загальноосвітньої школи І - ІІІ ступенів №1 Костянтинівської міської ради Донецької області за адресою: вул. Європейська,58 м. Костянтинівка
Строк виконання - 120 календарних днів, категорія складності - ІV
UAH12,054,632.40
including VATfrom Mar 30, 2017, 16:45
until Apr 23, 2017, 09:00
from Apr 24, 2017, 11:34
until Apr 24, 2017, 12:13
from Apr 24, 2017, 12:13
until May 12, 2017, 10:24
Pay attention!
00:00 - means the beginning of the day, not their end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
| № | Name | Quantity | Delivery | Place of delivery |
|---|---|---|---|---|
| 1 |
Робота
Code DK 021:2015:
45454000-4 Перебудовування
|
Quantity: 1 роботи |
Delivery period:
May 15, 2017 – Sep 15, 2017
|
Place of delivery: Україна, 84121, Донецька область, м. Слов’янськ, вул. Банківська, 79а |
Procurement documents
| Document name | Document type | Date of publishing |
| Not indicated | Apr 24, 2017, 12:13 | |
| Not indicated | Apr 24, 2017, 12:13 | |
|
|
||
| Procurement documents | Mar 30, 2017, 16:45 | |
| Electronic signature | Mar 30, 2017, 16:46 | |
| Draft contract | Mar 30, 2017, 16:45 | |
| Technical specifications | Mar 30, 2017, 16:45 | |
Non-price criteria
| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк, що складає менш ніж 60 % |
Option weight: 5.0 % |
|
Option name: у строк від 60 % до 80 % |
Option weight: 3.0 % |
|
|
Option name: у строк, що складає більше 80 %, включно до 99% |
Option weight: 1.0 % |
|
|
Option name: у строк, що дорівнює 100% |
Option weight: 0.0 % |
About procurement
Show more information
Hide detailed information
Auction history
View
Participants of auction
Documents submitted with the offer
| Document name | Document type | Date of publishing |
| Technical specifications | Apr 21, 2017, 21:59 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Estimate | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:59 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Estimate | Apr 21, 2017, 21:52 | |
| Compliance confirmation | Apr 21, 2017, 21:52 | |
| Price offer | Apr 21, 2017, 21:52 | |
| Documents confirming of qualification | Apr 21, 2017, 21:52 | |
| Technical specifications | Apr 21, 2017, 21:59 | |
| Compliance confirmation | Apr 21, 2017, 21:52 |
Offer
Status
disqualified| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк, що складає більше 80 %, включно до 99% |
Option weight: 1.0 % |
|
Total weight of all non-price criteria: 1.0 % |
||
|
Factor: 1.011 |
||
Documents submitted with the offer
| Document name | Document type | Date of publishing |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Price offer | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 | |
| Documents confirming of qualification | Apr 22, 2017, 17:18 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:17 | |
| Documents confirming of qualification | Apr 22, 2017, 17:16 |
Offer
Status
disqualified| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк, що складає менш ніж 60 % |
Option weight: 5.0 % |
|
Total weight of all non-price criteria: 5.0 % |
||
|
Factor: 1.053 |
||
Documents submitted with the offer
| Document name | Document type | Date of publishing |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 | |
| Technical specifications | Apr 23, 2017, 01:02 |
Offer
Status
disqualified| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк, що складає менш ніж 60 % |
Option weight: 5.0 % |
|
Total weight of all non-price criteria: 5.0 % |
||
|
Factor: 1.053 |
||
Documents submitted with the offer
| Document name | Document type | Date of publishing |
| Documents confirming of qualification | Apr 21, 2017, 13:49 | |
| Documents confirming of qualification | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:49 | |
| Technical specifications | Apr 27, 2017, 13:27 | |
| Documents confirming of qualification | Apr 21, 2017, 13:51 | |
| Estimate | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:51 | |
| Technical specifications | Apr 21, 2017, 13:51 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Price offer | Apr 21, 2017, 13:49 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Estimate | Apr 21, 2017, 13:51 | |
| Estimate | Apr 27, 2017, 13:27 | |
| Compliance confirmation | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 | |
| Documents confirming of qualification | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:51 | |
| Documents confirming of qualification | Apr 21, 2017, 13:50 |
Offer
Status
disqualified| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк від 60 % до 80 % |
Option weight: 3.0 % |
|
Total weight of all non-price criteria: 3.0 % |
||
|
Factor: 1.032 |
||
Documents submitted with the offer
| Document name | Document type | Date of publishing |
| Documents confirming of qualification | Apr 20, 2017, 16:03 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Technical specifications | Apr 20, 2017, 16:02 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Compliance confirmation | Apr 20, 2017, 16:02 | |
| Technical specifications | Apr 20, 2017, 16:02 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Estimate | Apr 20, 2017, 16:02 | |
| Compliance confirmation | Apr 20, 2017, 16:03 | |
| Documents confirming of qualification | Apr 20, 2017, 16:02 | |
| Compliance confirmation | Apr 20, 2017, 16:03 | |
| Compliance confirmation | Apr 20, 2017, 16:03 | |
| Compliance confirmation | Apr 20, 2017, 16:02 | |
| Compliance confirmation | Apr 20, 2017, 16:02 | |
| Price offer | Apr 20, 2017, 16:02 |
Decision of the responsible person
| Document name | Document type | Date of publishing |
| Not indicated | May 12, 2017, 10:23 | |
| Electronic signature | May 12, 2017, 10:24 |
Offer
Status
disqualified| Feature name | Option name | Option weight |
|
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.4.3 розділу І тендерної документації та обчислений календарними днями |
Option name: у строк від 60 % до 80 % |
Option weight: 3.0 % |
|
Total weight of all non-price criteria: 3.0 % |
||
|
Factor: 1.032 |
||
Useful links
List of public procurements of customer ДЕПАРТАМЕНТ КАПІТАЛЬНОГО БУДІВНИЦТВА ДОНЕЦЬКОЇ ОБЛАСНОЇ ДЕРЖАВНОЇ АДМІНІСТРАЦІЇYou may be interested
UAH6,327,597.60 including VAT
ViewUAH14,293,396.30 including VAT
ViewUAH11,090,016.00 including VAT
View