Розрядники
UAH1,986,366.67
without VATfrom Feb 2, 18:29
until Feb 8, 09:00
from Feb 8, 16:00
until Feb 19, 15:00
from Feb 19, 15:01
until Mar 11, 23:14
from Mar 11, 23:14
until Mar 20, 20:20
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Розрядник РВКУ-1,65 ДО1 ТУ У 31.2-25480461-001:2008
Code DK 021:2015:
31216100-4 Обладнання для захисту від блискавок
|
Quantity: 20 штуки |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
2 |
Розрядник РВКУ-3,3 АО1 ТУ У 31.2-25480461-001:2008
Code DK 021:2015:
31216100-4 Обладнання для захисту від блискавок
|
Quantity: 25 штуки |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
3 |
Розрядник РВЕ-25 ТУ У 27.12.10-38284929-002:2016
Code DK 021:2015:
31216100-4 Обладнання для захисту від блискавок
|
Quantity: 20 штуки |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Feb 2, 18:29 | |
Procurement documents | Feb 2, 18:29 |
Terms of payment
Non-price criteria
Feature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Умови розрахунків |
Option name: ЗАМОВНИК здійснює оплату за кожну партію фактично поставленого ТОВАРУ протягом 90 (дев’яносто) робочих днів з дати підписання Сторонами видаткової накладної (згідно умов договору). |
Option weight: 20.0 % |
Option name: ЗАМОВНИК здійснює оплату за кожну партію фактично поставленого ТОВАРУ протягом 60 (шістдесят) робочих днів з дати підписання Сторонами видаткової накладної (згідно умов договору). |
Option weight: 10.0 % |
|
Option name: ЗАМОВНИК здійснює оплату за кожну партію фактично поставленого ТОВАРУ протягом 45 (сорок п’ять) робочих днів з дати підписання Сторонами видаткової накладної (згідно умов договору). |
Option weight: 0.0 % |
|
Feature name: Строк поставкиDescription: Строк поставки |
Option name: Строк поставки ТОВАРУ ПОСТАЧАЛЬНИКОМ: протягом не більше 5 (п’яти) календарних днів з дати отримання ПОСТАЧАЛЬНИКОМ від ЗАМОВНИКА письмової заявки на постачання ТОВАРУ. |
Option weight: 10.0 % |
Option name: Строк поставки ТОВАРУ ПОСТАЧАЛЬНИКОМ: протягом не більше 10 (десяти) календарних днів з дати отримання ПОСТАЧАЛЬНИКОМ від ЗАМОВНИКА письмової заявки на постачання ТОВАРУ. |
Option weight: 3.0 % |
|
Option name: Строк поставки ТОВАРУ ПОСТАЧАЛЬНИКОМ: протягом не більше 20 (двадцяти) календарних днів з дати отримання ПОСТАЧАЛЬНИКОМ від ЗАМОВНИКА письмової заявки на постачання ТОВАРУ. |
Option weight: 1.0 % |
|
Option name: Строк поставки ТОВАРУ ПОСТАЧАЛЬНИКОМ: протягом не більше 30 (тридцяти) календарних днів з дати отримання ПОСТАЧАЛЬНИКОМ від ЗАМОВНИКА письмової заявки на постачання ТОВАРУ. |
Option weight: 0.0 % |
About tender
Show more information
Hide detailed information
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Not indicated | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Price offer | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Not indicated | Feb 19, 11:12 | |
Price offer | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Technical specifications | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 | |
Documents confirming of qualification | Feb 19, 11:12 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Mar 11, 23:14 | |
Not indicated | Mar 11, 23:14 |
Contract
Document name | Document type | Date of publishing |
Not indicated | Mar 20, 20:20 | |
Signed contract | Mar 20, 20:20 |
Offer
Status
winnerFeature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Умови розрахунків |
Option name: ЗАМОВНИК здійснює оплату за кожну партію фактично поставленого ТОВАРУ протягом 45 (сорок п’ять) робочих днів з дати підписання Сторонами видаткової накладної (згідно умов договору). |
Option weight: 0.0 % |
Feature name: Строк поставкиDescription: Строк поставки |
Option name: Строк поставки ТОВАРУ ПОСТАЧАЛЬНИКОМ: протягом не більше 30 (тридцяти) календарних днів з дати отримання ПОСТАЧАЛЬНИКОМ від ЗАМОВНИКА письмової заявки на постачання ТОВАРУ. |
Option weight: 0.0 % |
Total weight of all non-price criteria: 0.0 % |
||
Factor: 1.0 |
Contract
View of the contract