Паливо (дизельне паливо, бензин А-92)
UAH4,188,000.00
including VATfrom Nov 30, 2018, 16:19
until Dec 17, 2018, 10:00
from Dec 18, 2018, 12:45
until Dec 18, 2018, 13:12
from Dec 18, 2018, 13:12
until Dec 21, 2018, 15:27
from Dec 21, 2018, 15:27
until Jan 4, 2019, 15:27
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Дизельне паливо
Code DK 021:2015:
09130000-9 Нафта і дистиляти
|
Quantity: 123,000 л |
Delivery period:
Jan 2, 2018 – Dec 31, 2019
|
Place of delivery: Україна, 33018, Рівненська обл., Рівне, Курчатова, 22 |
2 |
Бензин А-92
Code DK 021:2015:
09130000-9 Нафта і дистиляти
|
Quantity: 12,500 л |
Delivery period:
до Dec 31, 2019
|
Place of delivery: Україна, 33018, Рівненська обл., Рівне, Курчатова, 22 |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Nov 30, 2018, 16:17 | |
Not indicated | Nov 30, 2018, 16:16 | |
Not indicated | Dec 18, 2018, 13:12 | |
Not indicated | Dec 18, 2018, 13:12 | |
|
Non-price criteria
Feature name | Option name | Option weight |
Feature name: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова, 22, км.Description: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова , 22 (км.) – 30 % - відстань від АЗС менше 1 км – 30 % - відстань від АЗС від 1 до 2 км – 20 % - відстань від АЗС від 2 до 3 км – 10 % - відстань від АЗС більше 3 км - 0% |
Option name: Відстань від АЗС більше 3 км. |
Option weight: 0.0 % |
Option name: Відстань від АЗС від 1 до 2 км. |
Option weight: 20.0 % |
|
Option name: Відстань від АЗС від 2 до 3 км. |
Option weight: 10.0 % |
|
Option name: Відстань від АЗС менше 1 км. |
Option weight: 30.0 % |
About tender
Show more information
Hide detailed information
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Price offer | Dec 14, 2018, 23:11 | |
Documents confirming of qualification | Dec 16, 2018, 19:33 | |
Compliance confirmation | Dec 26, 2018, 10:31 | |
Documents confirming of qualification | Dec 16, 2018, 19:33 | |
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
Compliance confirmation | Dec 26, 2018, 10:31 | |
Documents confirming of qualification | Dec 17, 2018, 09:34 | |
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
|
||
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
Compliance confirmation | Dec 26, 2018, 10:31 | |
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
Documents confirming of qualification | Dec 17, 2018, 09:46 | |
Documents confirming of qualification | Dec 16, 2018, 19:33 | |
|
||
Compliance confirmation | Dec 26, 2018, 10:31 | |
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
Documents confirming of qualification | Dec 14, 2018, 23:11 | |
Compliance confirmation | Dec 26, 2018, 10:31 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Dec 21, 2018, 15:26 | |
Not indicated | Dec 21, 2018, 15:26 | |
Extract from the register | Dec 18, 2018, 13:12 |
Contract
Document name | Document type | Date of publishing |
Not indicated | Jan 4, 2019, 15:27 | |
Signed contract | Jan 4, 2019, 15:27 |
Offer
Status
winnerFeature name | Option name | Option weight |
Feature name: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова, 22, км.Description: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова , 22 (км.) – 30 % - відстань від АЗС менше 1 км – 30 % - відстань від АЗС від 1 до 2 км – 20 % - відстань від АЗС від 2 до 3 км – 10 % - відстань від АЗС більше 3 км - 0% |
Option name: Відстань від АЗС менше 1 км. |
Option weight: 30.0 % |
Total weight of all non-price criteria: 30.0 % |
||
Factor: 1.429 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 17, 2018, 09:52 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 16, 2018, 23:47 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:44 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 17, 2018, 09:52 | |
Price offer | Dec 14, 2018, 17:43 | |
Not indicated | Dec 17, 2018, 09:53 | |
Not indicated | Dec 14, 2018, 17:46 | |
|
||
Not indicated | Dec 14, 2018, 17:43 | |
Not indicated | Dec 14, 2018, 17:43 |
Offer
Status
Not consideredFeature name | Option name | Option weight |
Feature name: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова, 22, км.Description: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова , 22 (км.) – 30 % - відстань від АЗС менше 1 км – 30 % - відстань від АЗС від 1 до 2 км – 20 % - відстань від АЗС від 2 до 3 км – 10 % - відстань від АЗС більше 3 км - 0% |
Option name: Відстань від АЗС менше 1 км. |
Option weight: 30.0 % |
Total weight of all non-price criteria: 30.0 % |
||
Factor: 1.429 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:16 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:16 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:16 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:16 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:16 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:16 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Price offer | Dec 15, 2018, 17:16 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Technical specifications | Dec 15, 2018, 17:16 | |
Documents confirming of qualification | Dec 15, 2018, 17:14 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Documents confirming of qualification | Dec 15, 2018, 17:15 | |
Technical specifications | Dec 15, 2018, 17:16 | |
Not indicated | Dec 15, 2018, 17:20 | |
Technical specifications | Dec 15, 2018, 17:14 |
Offer
Status
Not consideredFeature name | Option name | Option weight |
Feature name: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова, 22, км.Description: Відстань від АЗС учасника до бази підприємства м.Рівне, вул. Курчатова , 22 (км.) – 30 % - відстань від АЗС менше 1 км – 30 % - відстань від АЗС від 1 до 2 км – 20 % - відстань від АЗС від 2 до 3 км – 10 % - відстань від АЗС більше 3 км - 0% |
Option name: Відстань від АЗС більше 3 км. |
Option weight: 0.0 % |
Total weight of all non-price criteria: 0.0 % |
||
Factor: 1.0 |
Contract
View of the contract
Useful links
Public procurements list of the client КОМУНАЛЬНЕ АВТОТРАНСПОРТНЕ ПІДПРИЄМСТВО 1728You may be interested
UAH7,228,000.00 including VAT
ViewUAH2,516,400.00 including VAT
ViewUAH4,538,500.00 including VAT
View