Розробка проектно-кошторисної документації «Будівництво водопроводу від Карлівської фільтрувальної станції до населених пунктів м. Мар’їнка та м. Красногорівка на землях Мар’їнського району Донецької області»
UAH3,150,160.00
including VATfrom Apr 11, 2018, 17:01
until May 5, 2018, 14:00
from May 7, 2018, 13:41
until May 7, 2018, 14:32
from May 7, 2018, 14:32
until Jul 10, 2018, 16:12
from Jul 10, 2018, 16:12
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
The reason for cancellation of the procurement
Cause
canceled
Explanation
на виконання рішення АМКУ
Document name | Document type | Date of publishing |
Not indicated | Aug 30, 2018, 12:01 | |
Not indicated | Aug 30, 2018, 12:03 |
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Розробка проектно-кошторисної документації «Будівництво водопроводу від Карлівської фільтрувальної станції до населених пунктів м. Мар’їнка та м. Красногорівка на землях Мар’їнського району Донецької області»
Code DK 021:2015:
73300000-5 Проектування та виконання НДДКР
|
Quantity: 1 роботи |
Delivery period:
до Oct 31, 2019
|
Place of delivery: Україна, 85600, Донецька область, Мар'їнський район, Мар'їнський район |
Procurement documents
Document name | Document type | Date of publishing |
Draft contract | Apr 11, 2018, 17:02 | |
Draft contract | Apr 17, 2018, 17:21 | |
Not indicated | Apr 27, 2018, 10:48 | |
Not indicated | Apr 17, 2018, 17:22 | |
Not indicated | Apr 11, 2018, 17:02 | |
|
||
Procurement documents | Apr 27, 2018, 10:47 | |
Procurement documents | Apr 17, 2018, 17:22 | |
Clarification to participants' questions | Apr 27, 2018, 10:47 | |
Technical specifications | Apr 11, 2018, 17:02 | |
Draft contract | Apr 27, 2018, 10:47 | |
Procurement documents | Apr 11, 2018, 17:02 | |
Not indicated | May 7, 2018, 14:32 | |
Not indicated | May 7, 2018, 14:32 | |
|
||
Clarification to participants' questions | Apr 17, 2018, 17:21 |
Non-price criteria
Feature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: менш ніж 80 % |
Option weight: 5.0 % |
Option name: від 81 % до 90 % |
Option weight: 3.0 % |
|
Option name: більше 91 %, включно до 99% |
Option weight: 1.0 % |
|
Option name: 100% |
Option weight: 0.0 % |
About tender
Show more information
Hide detailed information
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | May 5, 2018, 09:42 | |
Documents confirming of qualification | May 5, 2018, 09:42 | |
Estimate | May 5, 2018, 09:42 | |
Price offer | May 5, 2018, 09:42 | |
Compliance confirmation | May 5, 2018, 09:42 | |
Technical specifications | May 5, 2018, 09:42 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Jun 20, 2018, 10:32 | |
Review Protocol | Jun 20, 2018, 10:31 | |
Extract from the register | Jun 13, 2018, 10:24 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: від 81 % до 90 % |
Option weight: 3.0 % |
Total weight of all non-price criteria: 3.0 % |
||
Factor: 1.032 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 10, 2018, 21:23 | |
Not indicated | May 5, 2018, 01:59 | |
|
||
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 10, 2018, 21:23 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 10, 2018, 21:23 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 10, 2018, 21:23 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 | |
Not indicated | May 5, 2018, 01:58 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Extract from the register | May 7, 2018, 14:32 | |
Not indicated | Jun 6, 2018, 12:56 | |
Not indicated | May 15, 2018, 15:26 | |
|
||
Not indicated | May 15, 2018, 15:25 | |
Review Protocol | Jun 6, 2018, 12:55 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: менш ніж 80 % |
Option weight: 5.0 % |
Total weight of all non-price criteria: 5.0 % |
||
Factor: 1.053 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Price offer | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | May 2, 2018, 13:04 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | May 1, 2018, 18:42 | |
Compliance confirmation | May 2, 2018, 14:32 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
|
||
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | May 2, 2018, 13:04 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | May 2, 2018, 13:04 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Not indicated | May 2, 2018, 14:33 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Compliance confirmation | Apr 27, 2018, 12:26 | |
Documents confirming of qualification | Apr 27, 2018, 12:26 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Review Protocol | Jun 13, 2018, 10:22 | |
Extract from the register | Jun 6, 2018, 12:56 | |
Not indicated | Jun 13, 2018, 10:23 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: менш ніж 80 % |
Option weight: 5.0 % |
Total weight of all non-price criteria: 5.0 % |
||
Factor: 1.053 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Price offer | Jun 20, 2018, 16:16 | |
Documents confirming of qualification | Jun 20, 2018, 16:16 | |
Documents confirming of qualification | May 4, 2018, 17:31 | |
Technical specifications | May 4, 2018, 17:31 | |
Documents confirming of qualification | May 4, 2018, 17:31 | |
Documents confirming of qualification | May 4, 2018, 17:31 | |
Not indicated | May 4, 2018, 17:33 | |
Documents confirming of qualification | May 4, 2018, 17:31 | |
Price offer | May 4, 2018, 17:31 | |
Estimate | May 4, 2018, 17:31 | |
Documents confirming of qualification | May 4, 2018, 17:31 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Review Protocol | Jun 23, 2018, 14:18 | |
Not indicated | Jun 23, 2018, 14:18 | |
Extract from the register | Jun 20, 2018, 10:32 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: менш ніж 80 % |
Option weight: 5.0 % |
Total weight of all non-price criteria: 5.0 % |
||
Factor: 1.053 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Estimate | May 4, 2018, 22:48 | |
Not indicated | May 5, 2018, 12:48 | |
Not indicated | May 4, 2018, 22:48 | |
|
||
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Price offer | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Technical specifications | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 | |
Documents confirming of qualification | May 4, 2018, 22:48 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Jun 26, 2018, 16:01 | |
Review Protocol | Jun 26, 2018, 14:49 | |
Extract from the register | Jun 23, 2018, 14:18 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: менш ніж 80 % |
Option weight: 5.0 % |
Total weight of all non-price criteria: 5.0 % |
||
Factor: 1.053 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | May 5, 2018, 13:46 | |
Technical specifications | May 5, 2018, 13:46 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Jul 3, 2018, 13:19 | |
Extract from the register | Jun 26, 2018, 16:01 | |
Review Protocol | Jul 3, 2018, 13:19 |
Offer
Status
disqualifiedFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: 100% |
Option weight: 0.0 % |
Total weight of all non-price criteria: 0.0 % |
||
Factor: 1.0 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 5, 2018, 16:30 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Price offer | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 5, 2018, 16:30 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 5, 2018, 16:30 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Price offer | Jul 5, 2018, 13:20 | |
Not indicated | Jul 16, 2018, 18:15 | |
Not indicated | Jul 16, 2018, 16:44 | |
Not indicated | Jul 6, 2018, 10:48 | |
Not indicated | Jul 5, 2018, 16:31 | |
Not indicated | Jul 5, 2018, 13:23 | |
Not indicated | May 5, 2018, 13:49 | |
|
||
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 6, 2018, 10:46 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 5, 2018, 13:20 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Not indicated | Jul 16, 2018, 16:43 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Not indicated | Jul 16, 2018, 18:14 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Not indicated | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | Jul 5, 2018, 16:30 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 | |
Documents confirming of qualification | May 5, 2018, 13:47 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Extract from the register | Jul 3, 2018, 13:19 | |
Not indicated | Jul 10, 2018, 16:12 | |
Review Protocol | Jul 10, 2018, 16:11 |
Offer
Status
winnerFeature name | Option name | Option weight |
Feature name: строк виконанняDescription: зазначається у відсотковому відношенні до запланованого Замовником строку виконання робіт, який вказаний у п.3.6. тендерної документації та обчислений календарними днями |
Option name: від 81 % до 90 % |
Option weight: 3.0 % |
Total weight of all non-price criteria: 3.0 % |
||
Factor: 1.032 |