Реконструкція будівлі КУ СЗОШ І-ІІІ ступенів № 22 по вул. Ковпака, 57
UAH24,495,079.20
including VATfrom Apr 19, 2017, 15:07
until May 4, 2017, 16:00
from May 5, 2017, 12:42
until May 5, 2017, 13:09
from May 5, 2017, 13:09
until May 11, 2017, 15:24
from May 11, 2017, 15:24
until May 29, 2017, 14:26
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Реконструкція будівлі КУ СЗОШ І-ІІІ ступенів № 22 по вул. Ковпака, 57
Code DK 021:2015:
45214200-2 Будівництво шкіл
|
Quantity: 1 роботи |
Delivery period:
May 22, 2017 – Dec 31, 2017
|
Place of delivery: Україна, 40000, Сумська область, Суми, Ковпака, 57 |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Apr 21, 2017, 13:14 | |
Not indicated | Apr 21, 2017, 13:12 | |
Not indicated | Apr 19, 2017, 15:07 | |
|
||
Estimate | Apr 19, 2017, 15:07 | |
Not indicated | May 5, 2017, 13:09 | |
Not indicated | May 5, 2017, 13:09 | |
|
||
Procurement documents | Apr 21, 2017, 13:11 | |
Procurement documents | Apr 21, 2017, 13:14 | |
Procurement documents | Apr 19, 2017, 15:07 | |
|
||
Estimate | Apr 19, 2017, 15:07 |
Non-price criteria
Feature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Бобчисл = Побчисл : Пmax х 10 |
Option name: Умови розрахунків |
Option weight: 10.0 % |
Option name: - |
Option weight: 0.0 % |
|
Feature name: Строк виконання робітDescription: Бобчисл = Рmin : Робчисл х 10 |
Option name: Строк виконання робіт |
Option weight: 10.0 % |
Option name: - |
Option weight: 0.0 % |
About tender
Show more information
Hide detailed information
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 4, 2017, 12:13 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 | |
Technical specifications | May 3, 2017, 12:58 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | May 11, 2017, 15:24 | |
Review Protocol | May 11, 2017, 15:22 | |
Review Protocol | May 11, 2017, 15:22 |
Contract
Document name | Document type | Date of publishing |
Not indicated | May 29, 2017, 14:26 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 | |
Signed contract | May 29, 2017, 14:25 |
Offer
Status
winnerFeature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Бобчисл = Побчисл : Пmax х 10 |
Option name: Умови розрахунків |
Option weight: 10.0 % |
Feature name: Строк виконання робітDescription: Бобчисл = Рmin : Робчисл х 10 |
Option name: Строк виконання робіт |
Option weight: 10.0 % |
Total weight of all non-price criteria: 20.0 % |
||
Factor: 1.25 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | May 4, 2017, 15:08 | |
Estimate | May 4, 2017, 15:08 | |
Estimate | May 4, 2017, 15:08 |
Offer
Status
Not consideredFeature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Бобчисл = Побчисл : Пmax х 10 |
Option name: Умови розрахунків |
Option weight: 10.0 % |
Feature name: Строк виконання робітDescription: Бобчисл = Рmin : Робчисл х 10 |
Option name: Строк виконання робіт |
Option weight: 10.0 % |
Total weight of all non-price criteria: 20.0 % |
||
Factor: 1.25 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Price offer | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Documents confirming of qualification | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Compliance confirmation | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Compliance confirmation | May 4, 2017, 12:46 | |
Documents confirming of qualification | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Compliance confirmation | May 4, 2017, 12:46 | |
Compliance confirmation | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 | |
Estimate | May 4, 2017, 12:46 |
Offer
Status
Not consideredFeature name | Option name | Option weight |
Feature name: Умови розрахунківDescription: Бобчисл = Побчисл : Пmax х 10 |
Option name: - |
Option weight: 0.0 % |
Feature name: Строк виконання робітDescription: Бобчисл = Рmin : Робчисл х 10 |
Option name: - |
Option weight: 0.0 % |
Total weight of all non-price criteria: 0.0 % |
||
Factor: 1.0 |
Contract