Послуги з повного технічного обслуговування ліфтів
Services for complete maintenance of elevators
UAH8,869,700.00
including VATfrom Jan 12, 2017, 17:17
until Feb 13, 2017, 17:22
from Feb 13, 2017, 17:23
until Mar 1, 2017, 00:00
from Mar 1, 2017, 15:58
until Mar 1, 2017, 16:19
from Mar 1, 2017, 16:19
until Mar 2, 2017, 15:24
from Mar 2, 2017, 15:24
until Mar 20, 2017, 12:23
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Послуги з повного технічного обслуговування ліфтів Services for complete maintenance of elevators
Code DK 021:2015:
50750000-7 Послуги з технічного обслуговування ліфтів
|
Quantity: 1 лот |
Delivery period:
Mar 1, 2017 – Mar 1, 2018
|
Place of delivery: Україна, 01021, м. Київ, м. Київ, пров. Мар'яненка, 7 |
Procurement documents
Document name | Document type | Date of publishing |
Procurement documents | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Technical specifications | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Not indicated | Jan 12, 2017, 17:25 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Draft contract | Jan 12, 2017, 17:17 | |
Not indicated | Mar 1, 2017, 16:19 | |
Not indicated | Mar 1, 2017, 16:19 | |
|
||
Procurement documents | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 | |
Procurement documents | Jan 12, 2017, 17:17 |
Non-price criteria
Feature name | Option name | Option weight |
Feature name: Строк виконання послугDescription: Гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів Строк виконання послуг Description: гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів |
Option name: до 10 хвилин включно 10 minutes including |
Option weight: 10.0 % |
Option name: більше 10 хвилин до години включно more than 10 minutes to an hour, including |
Option weight: 5.0 % |
|
Option name: більше години more than an hour |
Option weight: 0.0 % |
|
Feature name: Гарантійне обслуговуванняDescription: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO Гарантійне обслуговування Description: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO |
Option name: Наявність сертифікату системи якості ISO The certificate of quality system ISO |
Option weight: 10.0 % |
Option name: Відсутність сертифікату системи якості ISO Lack of quality system certificate ISO |
Option weight: 0.0 % |
|
Feature name: Умови оплатиDescription: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо Умови оплати Description: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо |
Option name: до одного місяця включно including one month |
Option weight: 0.0 % |
Option name: від одного Місяця до трьох місяців включно from one month to three months inclusive |
Option weight: 5.0 % |
|
Option name: більше трьох місяців three months |
Option weight: 10.0 % |
About tender
Show more information
Hide detailed information
Prequalification of participants
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Feb 13, 2017, 14:04 | |
Compliance confirmation | Feb 13, 2017, 14:04 | |
Compliance confirmation | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Compliance confirmation | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Compliance confirmation | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 | |
Documents confirming of qualification | Feb 13, 2017, 14:04 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Feb 23, 2017, 10:54 | |
Not indicated | Feb 23, 2017, 10:58 |
Status:
disqualified
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Documents confirming of qualification | Feb 13, 2017, 15:25 | |
Technical specifications | Feb 13, 2017, 15:19 | |
Documents confirming of qualification | Feb 13, 2017, 15:20 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:22 | |
Technical specifications | Feb 13, 2017, 15:19 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:22 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Feb 23, 2017, 11:00 | |
Not indicated | Feb 23, 2017, 11:02 |
Status:
Allowed to participate
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Compliance confirmation | Feb 13, 2017, 15:37 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:33 | |
Documents confirming of qualification | Feb 13, 2017, 15:34 | |
Documents confirming of qualification | Feb 13, 2017, 15:34 | |
Documents confirming of qualification | Feb 13, 2017, 15:31 | |
Documents confirming of qualification | Feb 13, 2017, 15:32 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:33 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Feb 23, 2017, 11:00 | |
Not indicated | Feb 23, 2017, 11:04 |
Status:
Allowed to participateAuction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 | |
Documents confirming of qualification | Feb 13, 2017, 15:25 | |
Technical specifications | Feb 13, 2017, 15:19 | |
Documents confirming of qualification | Feb 13, 2017, 15:20 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:22 | |
Technical specifications | Feb 13, 2017, 15:19 | |
Technical specifications | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:20 | |
Documents confirming of qualification | Feb 13, 2017, 15:22 | |
Documents confirming of qualification | Feb 13, 2017, 15:21 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Mar 2, 2017, 15:24 | |
License | Mar 2, 2017, 15:17 |
Contract
Document name | Document type | Date of publishing |
Not indicated | Mar 20, 2017, 12:23 | |
Signed contract | Mar 20, 2017, 12:21 |
Offer
Status
winnerFeature name | Option name | Option weight |
Feature name: Строк виконання послугDescription: Гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів Строк виконання послуг Description: гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів |
Option name: до 10 хвилин включно 10 minutes including |
Option weight: 10.0 % |
Feature name: Гарантійне обслуговуванняDescription: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO Гарантійне обслуговування Description: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO |
Option name: Наявність сертифікату системи якості ISO The certificate of quality system ISO |
Option weight: 10.0 % |
Feature name: Умови оплатиDescription: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо Умови оплати Description: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо |
Option name: більше трьох місяців three months |
Option weight: 10.0 % |
Total weight of all non-price criteria: 30.0 % |
||
Factor: 1.429 |
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Compliance confirmation | Feb 13, 2017, 15:37 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:33 | |
Documents confirming of qualification | Feb 13, 2017, 15:34 | |
Documents confirming of qualification | Feb 13, 2017, 15:34 | |
Documents confirming of qualification | Feb 13, 2017, 15:31 | |
Documents confirming of qualification | Feb 13, 2017, 15:32 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Documents confirming of qualification | Feb 13, 2017, 15:36 | |
Compliance confirmation | Feb 13, 2017, 15:38 | |
Documents confirming of qualification | Feb 13, 2017, 15:33 |
Offer
Status
Not consideredFeature name | Option name | Option weight |
Feature name: Строк виконання послугDescription: Гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів Строк виконання послуг Description: гарантований мінімальний час реагування на аварійну ситуацію у разі несанкціонованої зупинки ліфтів |
Option name: до 10 хвилин включно 10 minutes including |
Option weight: 10.0 % |
Feature name: Гарантійне обслуговуванняDescription: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO Гарантійне обслуговування Description: наявність у учасника сертифікату на відповідність системи управління якістю щодо технічного обслуговування ліфтів вимогам ДСТУ ISO 9001:2009 (надалі- сертифікату системи якості ISO |
Option name: Наявність сертифікату системи якості ISO The certificate of quality system ISO |
Option weight: 10.0 % |
Feature name: Умови оплатиDescription: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо Умови оплати Description: відстрочка платежу за виконання відновлювальних робіт після вандалізму, розкрадань, підпалів та залиття обладнання, тощо |
Option name: більше трьох місяців three months |
Option weight: 10.0 % |
Total weight of all non-price criteria: 30.0 % |
||
Factor: 1.429 |
Contract
View of the contract