Обладнання поставарійної моніторингової системи та аварійних контрольно-вимірювальних приладів (Приладове забезпечення під час і після аварій (ПАМС)) для ВП РАЕС
Post-accident monitoring system equipment and emergency instrumentation (instrumentation/measurement during and after an accident - PAMS) for SS RNPP
UAH283,872,000.00
including VATfrom Nov 17, 2016, 11:25
until Dec 26, 2016, 11:40
from Dec 26, 2016, 11:43
until Jan 24, 2017, 00:00
from Jan 24, 2017, 15:06
until Jan 24, 2017, 15:27
from Jan 24, 2017, 15:27
until Jan 25, 2017, 13:57
from Jan 25, 2017, 13:57
until Feb 15, 2017, 13:17
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Обладнання поставарійної моніторингової системи та аварійних контрольно-вимірювальних приладів (Приладове забезпечення під час і після аварій (ПАМС)) для ВП РАЕС Post-accident monitoring system equipment and emergency instrumentation (instrumentation/measurement during and after an accident - PAMS) for SS RNPP
Code DK 021:2015:
38810000-6 Обладнання для керування виробничими процесами
Code DK 016:2010:
26.51.7 Термостати, маностати та інші прилади й апаратура для автоматичного регулювання чи контролювання
|
Quantity: 2 шт |
Delivery period:
Dec 1, 2017 – Dec 31, 2017
|
Place of delivery: Україна, 34400, Рівненська обл., Вараш (Кузнецовськ ), Промислова зона 35/2, Будівельна база №1 |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Dec 14, 2016, 16:44 | |
Not indicated | Nov 17, 2016, 11:22 | |
Not indicated | Jan 24, 2017, 15:27 | |
Not indicated | Jan 24, 2017, 15:27 | |
|
||
Not indicated | Nov 17, 2016, 11:22 | |
Not indicated | Dec 14, 2016, 16:46 | |
Not indicated | Nov 17, 2016, 11:22 | |
|
||
Not indicated | Dec 14, 2016, 16:44 | |
Not indicated | Nov 17, 2016, 11:22 | |
|
||
Not indicated | Dec 14, 2016, 16:44 | |
Not indicated | Nov 17, 2016, 11:22 | |
|
||
Not indicated | Nov 17, 2016, 11:22 | |
Not indicated | Nov 17, 2016, 11:22 | |
Not indicated | Dec 14, 2016, 16:44 | |
Not indicated | Nov 17, 2016, 11:22 | |
|
||
Not indicated | Nov 17, 2016, 11:22 |
About tender
Show more information
Hide detailed information
Prequalification of participants
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Price offer | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Price offer | Jan 27, 2017, 09:58 | |
Compliance confirmation | Jan 27, 2017, 09:58 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Jan 27, 2017, 09:58 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Compliance confirmation | Jan 27, 2017, 19:30 | |
Price offer | Dec 26, 2016, 09:48 | |
Price offer | Dec 26, 2016, 09:48 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Jan 18, 2017, 15:53 | |
Not indicated | Jan 18, 2017, 15:52 |
Status:
Allowed to participate
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Price offer | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:30 | |
Documents confirming of qualification | Dec 26, 2016, 10:30 | |
Documents confirming of qualification | Dec 26, 2016, 10:29 | |
Documents confirming of qualification | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Jan 18, 2017, 15:54 | |
Not indicated | Jan 18, 2017, 15:54 |
Status:
Allowed to participate
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | Dec 26, 2016, 10:51 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:51 | |
Technical specifications | Dec 26, 2016, 10:51 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:51 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:51 | |
Technical specifications | Dec 26, 2016, 10:52 | |
Technical specifications | Dec 26, 2016, 10:52 |
Protocol for access to trading
Document name | Document type | Date of publishing |
Not indicated | Jan 18, 2017, 15:55 | |
Not indicated | Jan 18, 2017, 15:55 |
Status:
disqualifiedAuction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Price offer | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Price offer | Jan 27, 2017, 09:58 | |
Compliance confirmation | Jan 27, 2017, 09:58 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Compliance confirmation | Jan 27, 2017, 09:58 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Documents confirming of qualification | Dec 26, 2016, 09:48 | |
Compliance confirmation | Dec 26, 2016, 09:48 | |
Technical specifications | Dec 26, 2016, 09:48 | |
Compliance confirmation | Jan 27, 2017, 19:30 | |
Price offer | Dec 26, 2016, 09:48 | |
Price offer | Dec 26, 2016, 09:48 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Jan 25, 2017, 13:57 | |
Not indicated | Jan 25, 2017, 13:57 |
Contract
Document name | Document type | Date of publishing |
Signed contract | Feb 15, 2017, 13:17 | |
Not indicated | Feb 15, 2017, 13:17 |
Offer
Status
winner
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Price offer | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:30 | |
Documents confirming of qualification | Dec 26, 2016, 10:30 | |
Documents confirming of qualification | Dec 26, 2016, 10:29 | |
Documents confirming of qualification | Dec 26, 2016, 10:29 | |
Compliance confirmation | Dec 26, 2016, 10:29 | |
Technical specifications | Dec 26, 2016, 10:29 |
Offer
Status
Not consideredContract
View of the contract