ДК 021:2015 45454000-4 Реконструкція («Реконструкція комплексу будівель Комунального некомерційного підприємства «Міська лікарня швидкої медичної допомоги» за адресою: м. Кам'янське, вул. В'ячеслава Чорновола, 79А». Коригування 1.)
UAH187,990,141.00
including VATfrom Mar 6, 13:32
until Mar 18, 00:00
from Mar 18, 14:14
until Mar 18, 14:37
from Mar 18, 14:37
until Apr 12, 23:16
from Apr 12, 23:16
until Apr 30, 23:10
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Purchase information
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
ДК 021:2015 45454000-4 Реконструкція («Реконструкція комплексу будівель Комунального некомерційного підприємства «Міська лікарня швидкої медичної допомоги» за адресою: м. Кам'янське, вул. В'ячеслава Чорновола, 79А». Коригування 1.)
Code DK 021:2015:
45454000-4 Реконструкція
|
Quantity: 1 роботи |
Delivery period:
до Dec 31
|
Place of delivery: Україна, 51900, Дніпропетровська область, м. Кам'янське, вулиця В'ячеслава Чорновола, 79А |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Mar 13, 16:00 | |
Not indicated | Mar 6, 13:35 | |
|
||
Procurement documents | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Technical specifications | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 13, 15:55 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Draft contract | Mar 13, 15:55 | |
Draft contract | Mar 6, 13:33 | |
|
||
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 18, 14:37 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Procurement documents | Mar 13, 15:55 | |
Procurement documents | Mar 6, 13:33 | |
|
||
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 | |
Procurement documents | Mar 6, 13:33 | |
Not indicated | Mar 6, 13:33 |
Terms of payment lot
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Not indicated | Apr 15, 16:56 | |
Not indicated | Apr 15, 14:16 | |
Not indicated | Mar 17, 17:27 | |
Not indicated | Mar 16, 16:13 | |
|
||
Compliance confirmation | Apr 15, 14:14 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Compliance confirmation | Mar 16, 16:12 | |
Compliance confirmation | Apr 15, 14:14 | |
Compliance confirmation | Apr 15, 14:14 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Compliance confirmation | Apr 15, 14:14 | |
Compliance confirmation | Apr 15, 14:14 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Compliance confirmation | Apr 15, 14:14 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Compliance confirmation | Apr 15, 14:14 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Compliance confirmation | Apr 15, 16:55 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 17, 17:26 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Documents confirming of qualification | Mar 16, 16:12 | |
Not indicated | Mar 17, 17:27 | |
Not indicated | Mar 16, 16:13 | |
|
||
Documents confirming of qualification | Mar 16, 16:12 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Review Protocol | Mar 25, 21:57 | |
Extract from the register | Mar 18, 14:37 | |
Reference of NAZK
PDF version accepted in
personal account
|
Reference | Apr 12, 23:16 |
Not indicated | Apr 12, 23:16 | |
Not indicated | Mar 25, 21:57 | |
|
||
Review Protocol | Apr 12, 22:57 |
Contract
Document name | Document type | Date of publishing |
Not indicated | Apr 30, 22:59 | |
Signed contract | Apr 30, 22:59 | |
Not indicated | Apr 30, 22:59 | |
Annexes to the contract | Apr 30, 22:59 | |
Annexes to the contract | Apr 30, 22:59 | |
Not indicated | Apr 30, 23:10 |
Answers to requirements for purchase criteria
Customer request for information confirmation
-Document
Document name | Document type | Date of publishing |
Compliance confirmation | Mar 16, 16:12 |
Offer:
Status:
winner
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Estimate | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Compliance confirmation | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Not indicated | Mar 15, 17:50 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Price offer | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Compliance confirmation | Mar 15, 17:45 | |
Compliance confirmation | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 | |
Technical specifications | Mar 15, 17:45 |
Answers to requirements for purchase criteria
Customer request for information confirmation
-Document
Document name | Document type | Date of publishing |
Technical specifications | Mar 15, 17:45 |
Offer:
Status:
Not consideredContract
View of the contract