Лот 1. №1 ТЕЦ-5 із заміною спіралей за адресою: м.Київ, вул.Промислова,4
UAH3,321,746.00
including VATfrom Feb 16, 12:02
until Feb 28, 10:00
from Feb 29, 13:28
until Feb 29, 14:03
from Feb 29, 14:03
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Purchase information
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Роботи з відновлення ресурсу працездатності підігрівачів високого тиску №5,6,7 енергоблоку ст.№1 ТЕЦ-5 із заміною спіралей за адресою: м.Київ, вул.Промислова,4
Code DK 021:2015:
45315000-8 Встановлення електричних систем опалення та іншого побутового електричного обладнання
|
Quantity: 1 робота |
Delivery period:
до Oct 18
|
Place of delivery: Україна, Відповідно до документації |
Procurement documents
Document name | Document type | Date of publishing |
Procurement documents | Feb 22, 16:47 | |
Draft contract | Feb 16, 12:02 | |
Procurement documents | Feb 16, 12:02 | |
Draft contract | Feb 22, 15:17 | |
Procurement documents | Feb 22, 15:17 | |
Procurement documents | Feb 16, 12:02 | |
Procurement documents | Feb 16, 12:02 | |
Not indicated | Feb 22, 16:47 | |
Technical specifications | Feb 21, 17:26 | |
Not indicated | Feb 22, 16:47 | |
Not indicated | Feb 22, 15:18 | |
Not indicated | Feb 21, 17:26 | |
Not indicated | Feb 16, 12:03 | |
|
||
Draft contract | Feb 22, 16:47 | |
Technical specifications | Feb 16, 12:02 | |
Not indicated | Feb 29, 14:03 | |
Not indicated | Feb 22, 15:17 | |
Procurement documents | Feb 16, 12:02 |
Terms of payment lot
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Not indicated | Feb 23, 09:04 | |
Not indicated | Feb 22, 08:24 | |
Not indicated | Feb 21, 11:29 | |
|
||
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Documents confirming of qualification | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 | |
Not indicated | Feb 23, 09:04 | |
Not indicated | Feb 22, 08:24 | |
Not indicated | Feb 21, 11:29 | |
|
||
Compliance confirmation | Feb 21, 11:29 | |
Compliance confirmation | Feb 21, 11:29 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Mar 6, 17:13 | |
Extract from the register | Feb 29, 14:09 | |
Not indicated | Mar 6, 17:12 |
Answers to requirements for purchase criteria
Offer:
Status:
waiting for a decision
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Estimate | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Estimate | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Not indicated | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Estimate | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Estimate | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 | |
Not indicated | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Compliance confirmation | Feb 27, 12:00 | |
Documents confirming of qualification | Feb 27, 12:00 |
Answers to requirements for purchase criteria
Offer:
Status:
waiting for a review
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Estimate | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Compliance confirmation | Feb 28, 01:23 | |
Not indicated | Feb 28, 01:25 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Documents confirming of qualification | Feb 28, 01:23 | |
Not indicated | Feb 28, 01:25 |
Answers to requirements for purchase criteria
Offer:
Status:
waiting for a review
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Not indicated | Feb 27, 22:08 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 | |
Technical specifications | Feb 27, 22:05 |
Answers to requirements for purchase criteria
Offer:
Status:
waiting for a review