Хлор рідкий у контейнерах, коагулянти (ДК 021:2015 – 24310000-0 - Основні неорганічні хімічні речовини)
UAH270,000,000.00
including VATfrom Dec 15, 2023, 14:56
until Feb 8, 00:00
from Feb 8, 15:47
until Feb 8, 16:16
from Feb 8, 16:16
until Mar 14, 14:52
from Mar 14, 14:52
until Mar 29, 11:22
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Purchase information
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Коагулянт Гідроксихлорид алюмінію
Code DK 021:2015:
24310000-0 Основні неорганічні хімічні речовини
|
Quantity: 3,000 тонни |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
2 |
Коагулянт Гідроксихлорид алюмінію (високоосновний)
Code DK 021:2015:
24310000-0 Основні неорганічні хімічні речовини
|
Quantity: 1,000 тонни |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
3 |
Хлор рідкий в контейнерах
Code DK 021:2015:
24311900-6 Хлор
|
Quantity: 1,200 тонни |
Delivery period:
до Dec 31
|
Place of delivery: Україна, Відповідно до документації |
Procurement documents
Document name | Document type | Date of publishing |
Procurement documents | Jan 18, 13:05 | |
Procurement documents | Feb 3, 14:04 | |
Procurement documents | Feb 3, 14:04 | |
Procurement documents | Jan 12, 14:17 | |
Procurement documents | Dec 18, 2023, 11:00 | |
Procurement documents | Dec 18, 2023, 11:00 | |
Procurement documents | Jan 12, 14:17 | |
Procurement documents | Feb 3, 14:04 | |
Not indicated | Feb 8, 16:16 | |
Not indicated | Feb 3, 14:06 | |
Not indicated | Jan 18, 13:05 | |
Not indicated | Jan 15, 10:41 | |
Not indicated | Jan 12, 14:25 | |
Not indicated | Dec 18, 2023, 11:01 | |
Not indicated | Dec 15, 2023, 14:56 | |
|
||
Procurement documents | Dec 18, 2023, 11:00 | |
Procurement documents | Jan 15, 10:41 | |
Procurement documents | Jan 15, 10:41 | |
Procurement documents | Jan 12, 14:17 | |
Procurement documents | Dec 15, 2023, 14:56 | |
Procurement documents | Jan 18, 13:05 | |
Procurement documents | Jan 15, 10:41 | |
Procurement documents | Dec 15, 2023, 14:56 |
Terms of payment lot
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Not indicated | Feb 6, 15:03 | |
Not indicated | Jan 25, 10:25 | |
|
||
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Not indicated | Feb 6, 15:03 | |
Not indicated | Jan 25, 10:25 | |
|
||
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 | |
Documents confirming of qualification | Jan 25, 10:23 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Extract from the register | Feb 8, 16:16 | |
Not indicated | Feb 15, 08:59 | |
Not indicated | Feb 15, 08:59 |
Answers to requirements for purchase criteria
Offer:
Status:
disqualified
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Price offer | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Not indicated | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Price offer | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Not indicated | Feb 24, 12:11 | |
Not indicated | Feb 7, 13:14 | |
|
||
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Documents confirming of qualification | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 | |
Technical specifications | Feb 7, 13:14 | |
Compliance confirmation | Feb 24, 12:10 | |
Technical specifications | Feb 7, 13:14 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Not indicated | Feb 22, 13:24 | |
Extract from the register | Feb 15, 09:08 | |
Not indicated | Feb 27, 15:57 | |
Not indicated | Feb 27, 15:58 | |
Not indicated | Feb 22, 13:24 | |
|
Answers to requirements for purchase criteria
Offer:
Status:
disqualified
Documents submitted with the offer
Document name | Document type | Date of publishing |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Compliance confirmation | Mar 15, 15:26 | |
Compliance confirmation | Mar 15, 15:40 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Not indicated | Mar 15, 16:10 | |
Not indicated | Mar 13, 19:10 | |
Not indicated | Feb 7, 19:48 | |
|
||
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Documents confirming of qualification | Mar 13, 19:09 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:47 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Documents confirming of qualification | Mar 13, 19:09 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:39 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:58 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Documents confirming of qualification | Mar 13, 19:09 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 16:09 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:59 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Documents confirming of qualification | Mar 13, 19:09 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:26 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:45 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:40 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:59 | |
Technical specifications | Feb 7, 19:46 | |
Compliance confirmation | Mar 15, 15:27 | |
Technical specifications | Feb 7, 19:46 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Reference of NAZK
PDF version accepted in
personal account
|
Reference | Mar 14, 14:52 |
Not indicated | Mar 14, 14:52 | |
Not indicated | Mar 14, 14:52 | |
Not indicated | Mar 4, 12:41 | |
|
||
Extract from the register | Feb 27, 15:58 | |
Not indicated | Mar 4, 11:25 |
Contract
Document name | Document type | Date of publishing |
Signed contract | Mar 29, 11:21 | |
Not indicated | Mar 29, 11:22 |
Answers to requirements for purchase criteria
Offer:
Status:
winnerContract
View of the contract