Lot

Капітальний ремонт тротуару по вул.Незалежності (на ділянках: від буд. №4 до вул.Соборна 29 та від буд.№20 до буд.26а) в м.Ананьєві, Подільського району, Одеської області (видатки із благоустрою населених пунктів) (Код ДК 021:2015: 45230000-8 Будівництво трубопроводів, ліній зв’язку та електропередач, шосе, доріг, аеродромів і залізничних доріг; вирівнювання поверхонь)

Expected value

UAH2,266,429.40

including VAT
Completed
Call for proposals

from Jun 16, 2023, 09:01

until Jun 24, 2023, 00:00

Auction
not conducted
Qualification

from Jun 24, 2023, 00:01

until Jun 27, 2023, 14:49

Offers considered

from Jun 27, 2023, 14:49

until Jul 4, 2023, 09:24

Offers to be submitted:
Jun 16, 2023, 09:01 – Jun 24, 2023, 00:00

Pay attention!

00:00 - means the beginning of the day, not its end

Clarification period:
Jun 16, 2023, 09:01 – Jun 21, 2023, 00:00

Pay attention!

00:00 - means the beginning of the day, not its end

Replies to inquiries before:
Jun 24, 2023, 00:00
Appealing tender terms:
Jun 16, 2023, 09:01 – Jun 21, 2023, 00:00

Pay attention!

00:00 - means the beginning of the day, not its end

Date of the last changes to the tender conditions:
Jun 16, 2023, 09:14

Show all important dates

Hide dates

Information about customer

Name:
EDRPOU code:
43919503
Web site:
Not indicated
Address:
Україна, 66400, Одеська область, Ананьїв, вул.Незалежності,20
Rating:

This company has not been reviewed yet

To leave a review about a company and see its rating, you must sign up or Sign in

Main contact

Name:
Лисогора Володимир Олександрович ( )
Language skills:
Phone:
+380930183549
E-mail:
Fax:

Show customer contacts

Hide customer contacts

Purchase information

Expected value:
UAH2,266,429.40 including VAT
Minimum price decrement:
UAH22,664.29
ID procurement:
UA-2023-06-16-000695-a

Items list

Name Quantity Delivery Place of delivery
1

Капітальний ремонт тротуару по вул.Незалежності (на ділянках: від буд. №4 до вул.Соборна 29 та від буд.№20 до буд.26а) в м.Ананьєві, Подільського району, Одеської області (видатки із благоустрою населених пунктів) (Код ДК 021:2015: 45230000-8 Будівництво трубопроводів, ліній зв’язку та електропередач, шосе, доріг, аеродромів і залізничних доріг; вирівнювання поверхонь)

Code DK 021:2015: 45230000-8 Будівництво трубопроводів, ліній зв’язку та електропередач, шосе, доріг, аеродромів і залізничних доріг; вирівнювання поверхонь

Quantity:

1 роботи

Delivery period:

до Dec 31, 2023

Place of delivery:

Україна, 66401, Одеська область, Подільський район, м.Ананьїв, вул.Незалежності (на ділянках: від буд. №4 до вул.Соборна 29 та від буд.№20 до буд.26а)

Procurement documents

Document name Document type Date of publishing
Technical specifications Jun 16, 2023, 09:01
Procurement documents Jun 16, 2023, 09:01
Not indicated Jun 16, 2023, 09:01
Not indicated Jun 16, 2023, 09:14
Draft contract Jun 16, 2023, 09:01

Terms of payment lot

Payment after the event:
execution of works
Payment type:
postpayment
Payment amount:
100%
Period (in days):
10 ( banking )
Description:
Розрахунок за роботи здійснюється в безготівковому порядку, в національній валюті України шляхом перерахування грошових коштів на поточний рахунок Підрядника робіт - по мірі надходження бюджетних коштів на рахунок Замовника та по факту виконання робіт. Розрахунки проводяться по факту виконання робіт, протягом 10-и банківських днів з дня підписання сторонами Актів приймання виконаних будівельних робіт (Форма№ КБ-2в) та довідки про вартість виконаних будівельних робіт та витрати за формою№КБ-3, в залежності від фінансування з місцевого бюджету, при необхідності можливе відтермінування платежу. До актів виконаних робіт Підрядник, при необхідності, надає Замовнику виконавчу документацію, яка складена у відповідності до діючих нормативних документів. У разі ненадання або невідповідності виконавчої документації діючим нормам Замовник має право відкласти підписання актів за формами КБ-2в, КБ-3.

Participants of auction

Name:
Грицький Олександр Володимирович
E-mail: fopgritskiy@gmail.com Phone: +380486321930 EDRPOU:
3343216436

This company hasn't been reviewed yet, be the first to do so

To leave a review about a company and see its rating, you must sign up or Sign in
Attention, the mark "CEP" does not determine the type of applied signature! If an outdated type of EDS is used, the name will still indicate "CEP"
Contract was uploaded and signed by the customer. Tender completed.

Documents submitted with the offer

Document name Document type Date of publishing
Technical specifications Jun 23, 2023, 19:51
Estimate Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 29, 2023, 13:44
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 28, 2023, 19:17
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Not indicated Jun 29, 2023, 13:47
Not indicated Jun 28, 2023, 19:18
Not indicated Jun 23, 2023, 20:03
Not indicated Jun 16, 2023, 14:58
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 29, 2023, 13:44
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 29, 2023, 13:44
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 28, 2023, 19:17
Compliance confirmation Jun 28, 2023, 19:17
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 16, 2023, 14:57
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 29, 2023, 13:44
Compliance confirmation Jun 29, 2023, 13:44
Technical specifications Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:52
Compliance confirmation Jun 28, 2023, 19:17
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Technical specifications Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:52
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 16, 2023, 14:57
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Documents confirming of qualification Jun 23, 2023, 19:51
Compliance confirmation Jun 23, 2023, 19:51
Technical specifications Jun 23, 2023, 19:51

Decision of the responsible person

Document name Document type Date of publishing
Not indicated Jun 27, 2023, 14:49
Extract from the register Jun 24, 2023, 00:01
Extract from the register Jun 24, 2023, 00:01
Reference of NAZK
PDF version accepted in personal account
Reference Jun 27, 2023, 14:49
License Jun 27, 2023, 14:47

Contract

Document name Document type Date of publishing
Signed contract Jul 4, 2023, 09:08
Not indicated Jul 4, 2023, 09:24

Answers to requirements for purchase criteria

Requirements for the procurement participant
9 requirements
Вчинення злочинів, учинених з корисливих мотивів
Фізична особа, яка є учасником процедури закупівлі, не була засуджена за кримінальне правопорушення, вчинене з корисливих мотивів (зокрема, пов’язане з хабарництвом та відмиванням коштів), судимість з якої не знято або не погашено в установленому законом порядку
Вчинення економічних правопорушень
Суб’єкт господарювання (учасник процедури закупівлі) протягом останніх трьох років не притягувався до відповідальності за порушення, передбачене пунктом 4 частини другої статті 6, пунктом 1 статті 50 Закону України "Про захист економічної конкуренції", у вигляді вчинення антиконкурентних узгоджених дій, що стосуються спотворення результатів тендерів
Вчинення корупційних правопорушень
Відомості про юридичну особу, яка є учасником процедури закупівлі, не внесено до Єдиного державного реєстру осіб, які вчинили корупційні або пов'язані з корупцією правопорушення
Вчинення правопорушень, пов'язаних з використанням дитячої праці чи будь-якими формами торгівлі людьми
Керівника учасника процедури закупівлі, фізичну особу, яка є учасником процедури закупівлі, не було притягнуто згідно із законом до відповідальності за вчинення правопорушення, пов’язаного з використанням дитячої праці чи будь-якими формами торгівлі людьми
Порушення справ про банкрутство
Учасник процедури закупівлі не визнаний у встановленому законом порядку банкрутом та стосовно нього не відкрита ліквідаційна процедура
Наявність інших підстав для відмови в участі у процедурі закупівлі
У Єдиному державному реєстрі юридичних осіб, фізичних осіб - підприємців та громадських формувань присутня інформація, передбачена пунктом 9 частини другої статті 9 Закону України "Про державну реєстрацію юридичних осіб, фізичних осіб - підприємців та громадських формувань" (крім нерезидентів)
Мова (мови), якою (якими) повинні готуватися тендерні пропозиції
Мова тендерної пропозиції українська

Offer:

UAH2,209,768.68 including VAT

Status:

winner

Contract