Lot

Проєктування: Реконструкція ПЛ 220 кВ Трихати – Доброславська з відгалуженням на ПС 220 кВ «Березань» (інв. № 13713/0503) на ділянці опор №№ 18 – 130. Миколаївська область, Миколаївський район 71320000-7 Послуги з інженерного проектування

Expected value

UAH3,823,920.58

without VAT
Completed
Call for proposals

from Jun 7, 2023, 16:28

until Jun 19, 2023, 12:00

Auction
not conducted
Qualification

from Jun 19, 2023, 12:00

until Jun 26, 2023, 16:02

Offers considered

from Jun 26, 2023, 16:02

until Jul 6, 2023, 09:56

Offers to be submitted:
Jun 7, 2023, 16:28 – Jun 19, 2023, 12:00
Clarification period:
Jun 7, 2023, 16:28 – Jun 16, 2023, 00:00

Pay attention!

00:00 - means the beginning of the day, not its end

Replies to inquiries before:
Jun 19, 2023, 12:00
Appealing tender terms:
Jun 7, 2023, 16:28 – Jun 16, 2023, 00:00

Pay attention!

00:00 - means the beginning of the day, not its end

Date of the last changes to the tender conditions:
Jun 7, 2023, 16:28

Show all important dates

Hide dates

Information about customer

Name:
EDRPOU code:
00100227
Web site:
Address:
Україна, 01032, Київська область, Київ, вул. С.Петлюри, 25, м. Київ
Rating:
To leave a review about a company and see its rating, you must sign up or Sign in

Main contact

Name:
Костенко Оксана Вікторівна
Language skills:
Phone:
380442383741
E-mail:
Fax:

Show customer contacts

Hide customer contacts

Purchase information

Expected value:
UAH3,823,920.58 without VAT
Minimum price decrement:
UAH38,239.21
ID procurement:
UA-2023-06-07-013944-a

Items list

Name Quantity Delivery Place of delivery
1

Проєктування: Реконструкція ПЛ 220 кВ Трихати – Доброславська з відгалуженням на ПС 220 кВ «Березань» (інв. № 13713/0503) на ділянці опор №№ 18 – 130. Миколаївська область, Миколаївський район

Code DK 021:2015: 71320000-7 Послуги з інженерного проектування

Quantity:

1 роботи

Delivery period:

до Sep 1

Place of delivery:

Україна, Відповідно до документації

Procurement documents

Document name Document type Date of publishing
Procurement documents Jun 7, 2023, 16:28
Procurement documents Jun 7, 2023, 16:28
Not indicated Jun 7, 2023, 16:28

Terms of payment lot

Payment after the event:
date of invoicing
Payment type:
prepayment
Payment amount:
20%
Period (in days):
25 ( banking )
Description:
авансовий платіж 20% на виконання передпроєктних робіт: обстеження об’єкту, обмірні роботи, збір вихідних даних, вишукувальні роботи (інженерно-геологічні та інженерно-геодезичні роботи), тощо, протягом 25 банківських днів з дати отримання від Підрядника рахунку-фактури, але не більше 20% від загальної вартості договору.
Payment after the event:
execution of works
Payment type:
postpayment
Payment amount:
80%
Period (in days):
25 ( banking )
Description:
Подальша оплата здійснюється Замовником, після повного виконання Підрядником авансу на суму авансового платежу, протягом 25 банківських днів з дати підписання Сторонами двох примірників Акта (ів) здачі-приймання виконаних робіт (за примірною формою згідно з Настанови з визначення вартості проєктних, науково-проєктних, вишукувальних робіт та експертизи проєктної документації на будівництво) та за наданим Підрядником (після підписання Замовником зазначених Актів) рахунком-фактурою.

Participants of auction

Name:
Корня Олександр
E-mail: OKENERGY.ODESSA@GMAIL.COM Phone: 380668356077, 380668356077 EDRPOU:
41347370

This company hasn't been reviewed yet, be the first to do so

To leave a review about a company and see its rating, you must sign up or Sign in
Attention, the mark "CEP" does not determine the type of applied signature! If an outdated type of EDS is used, the name will still indicate "CEP"
Contract was uploaded and signed by the customer. Tender completed.

Documents submitted with the offer

Document name Document type Date of publishing
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Not indicated Jun 28, 2023, 12:50
Not indicated Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Price offer Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Price offer Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Compliance confirmation Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Price offer Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Price offer Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 28, 2023, 12:50
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03
Documents confirming of qualification Jun 19, 2023, 09:03

Decision of the responsible person

Document name Document type Date of publishing
Extract from the register Jun 19, 2023, 12:00
Not indicated Jun 26, 2023, 16:02
Reference of NAZK
PDF version accepted in personal account
Reference Jun 26, 2023, 16:02
Not indicated Jun 26, 2023, 16:02

Contract

Document name Document type Date of publishing
Signed contract Jul 6, 2023, 09:56
Not indicated Jul 6, 2023, 09:56
Signed contract Jul 6, 2023, 09:56

Answers to requirements for purchase criteria

Requirements for the procurement participant
10 requirements
Вчинення злочинів, учинених з корисливих мотивів
Керівник учасника процедури закупівлі не був засуджений за кримінальне правопорушення, вчинене з корисливих мотивів (зокрема, пов’язане з хабарництвом, шахрайством та відмиванням коштів), судимість з якого не знято або не погашено в установленому законом порядку
Вчинення економічних правопорушень
Суб’єкт господарювання (учасник процедури закупівлі) протягом останніх трьох років не притягувався до відповідальності за порушення, передбачене пунктом 4 частини другої статті 6, пунктом 1 статті 50 Закону України "Про захист економічної конкуренції", у вигляді вчинення антиконкурентних узгоджених дій, що стосуються спотворення результатів тендерів
Вчинення корупційних правопорушень
Відомості про юридичну особу, яка є учасником процедури закупівлі, не внесено до Єдиного державного реєстру осіб, які вчинили корупційні або пов'язані з корупцією правопорушення
Вчинення правопорушень, пов'язаних з використанням дитячої праці чи будь-якими формами торгівлі людьми
Керівника учасника процедури закупівлі, фізичну особу, яка є учасником процедури закупівлі, не було притягнуто згідно із законом до відповідальності за вчинення правопорушення, пов’язаного з використанням дитячої праці чи будь-якими формами торгівлі людьми
Порушення справ про банкрутство
Учасник процедури закупівлі не визнаний у встановленому законом порядку банкрутом та стосовно нього не відкрита ліквідаційна процедура
Наявність інших підстав для відмови в участі у процедурі закупівлі
У Єдиному державному реєстрі юридичних осіб, фізичних осіб - підприємців та громадських формувань присутня інформація, передбачена пунктом 9 частини другої статті 9 Закону України "Про державну реєстрацію юридичних осіб, фізичних осіб - підприємців та громадських формувань" (крім нерезидентів)
Мова (мови), якою (якими) повинні готуватися тендерні пропозиції
Мова тендерної пропозиції українська
Розмір та умови надання забезпечення виконання договору
Розмір та умови надання забезпечення виконання договору про закупівлю

Offer:

UAH2,800,000.00 without VAT

Status:

winner

Contract