Нанесення горизонтальної дорожньої розмітки з застосуванням холодного двокомпонентного структурного пластику
UAH1,299,474.50
including VATfrom Mar 16, 2023, 11:16
until Mar 27, 2023, 09:00
from Mar 27, 2023, 09:01
until Mar 31, 2023, 10:39
from Mar 31, 2023, 10:39
until Apr 13, 2023, 12:12
Attention!
The auction stage was skipped during the purchase. The winner will be determined by the price that participants indicate when submitting an offer.
Pay attention!
00:00 - means the beginning of the day, not its end
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Purchase information
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Нанесення горизонтальної дорожньої розмітки з застосуванням холодного двокомпонентного структурного пластику
Code DK 021:2015:
45230000-8 Будівництво трубопроводів, ліній зв’язку та електропередач, шосе, доріг, аеродромів і залізничних доріг; вирівнювання поверхонь
|
Quantity: 3,895 Погонний метр |
Delivery period:
до Oct 1, 2023
|
Place of delivery: Україна, Відповідно до документації |
Procurement documents
Document name | Document type | Date of publishing |
Procurement documents | Mar 16, 2023, 11:16 | |
Procurement documents | Mar 16, 2023, 11:16 | |
|
||
Not indicated | Mar 16, 2023, 11:17 | |
Not indicated | Mar 16, 2023, 11:17 | |
Not indicated | Mar 16, 2023, 11:17 | |
|
||
Not indicated | Mar 21, 2023, 14:09 |
Terms of payment lot
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Not indicated | Apr 3, 2023, 15:42 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Price offer | Mar 26, 2023, 22:52 | |
Compliance confirmation | Mar 31, 2023, 11:41 | |
Not indicated | Mar 26, 2023, 22:52 | |
Not indicated | Mar 26, 2023, 22:52 | |
Not indicated | Mar 26, 2023, 22:54 | |
Not indicated | Mar 26, 2023, 22:54 | |
Not indicated | Mar 26, 2023, 22:54 | |
Not indicated | Mar 26, 2023, 22:54 | |
Not indicated | Mar 26, 2023, 22:54 | |
|
||
Compliance confirmation | Mar 31, 2023, 11:36 | |
Not indicated | Mar 26, 2023, 22:52 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Not indicated | Mar 26, 2023, 22:52 | |
Documents confirming of qualification | Mar 26, 2023, 22:52 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Not indicated | Mar 26, 2023, 22:52 | |
Compliance confirmation | Mar 31, 2023, 11:41 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Compliance confirmation | Mar 31, 2023, 11:41 | |
Not indicated | Mar 26, 2023, 22:52 | |
Not indicated | Mar 26, 2023, 22:52 | |
Not indicated | Mar 26, 2023, 22:52 | |
Price offer | Mar 26, 2023, 22:52 | |
Documents confirming of qualification | Mar 26, 2023, 22:52 | |
Compliance confirmation | Mar 31, 2023, 11:41 | |
Not indicated | Apr 3, 2023, 15:42 | |
Not indicated | Mar 26, 2023, 22:52 | |
Estimate | Apr 3, 2023, 15:42 | |
Price offer | Mar 26, 2023, 22:52 | |
Not indicated | Apr 3, 2023, 15:47 | |
Not indicated | Mar 26, 2023, 22:52 | |
Estimate | Apr 3, 2023, 15:47 | |
Compliance confirmation | Mar 31, 2023, 11:41 | |
Compliance confirmation | Mar 31, 2023, 11:36 | |
Not indicated | Apr 3, 2023, 15:47 | |
Documents confirming of qualification | Mar 26, 2023, 22:52 | |
Not indicated | Mar 26, 2023, 22:52 | |
Not indicated | Apr 3, 2023, 15:48 |
Decision of the responsible person
Document name | Document type | Date of publishing |
Extract from the register | Mar 27, 2023, 09:02 | |
Mar 31, 2023, 10:30 | ||
Mar 31, 2023, 10:30 | ||
|
||
Not indicated | Mar 31, 2023, 10:31 | |
Not indicated | Mar 31, 2023, 10:31 | |
|
||
Mar 31, 2023, 10:30 | ||
Mar 31, 2023, 10:30 | ||
|
Contract
Document name | Document type | Date of publishing |
Not indicated | Apr 13, 2023, 12:11 | |
Signed contract | Apr 13, 2023, 12:11 |
Answers to requirements for purchase criteria
Offer:
Status:
winner
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 19:57 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Not indicated | Mar 26, 2023, 20:05 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 | |
Documents confirming of qualification | Mar 26, 2023, 17:16 |
Answers to requirements for purchase criteria
Offer:
Status:
Not consideredContract