Changes to contract
Change №1
Status:
Change cause:
Note:
сторони погодилися зменшити ціну договору в звязку з коригуванням проектної документації
ID:
89fc4436db37499bbead07e0f2ac1db5
Date:
Jul 2, 2024, 12:29
Number of loaded document:
1
Date of signature:
Jul 2, 2024, 15:26
|
|
Not indicated
|
Jul 2, 2024, 15:27
|
|
|
Signed contract
|
Jul 2, 2024, 15:27
|
|
|
Electronic signature
|
Jul 2, 2024, 15:29
|
|
|
Not indicated
|
Jul 2, 2024, 15:27
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв'язку з продовженням строку на виконання робіт внести зміни до додатку №2
ID:
7fcbefde597e4d65b4dc0b6609d3b197
Date:
Oct 2, 2024, 13:32
Number of loaded document:
2
Date of signature:
Oct 2, 2024, 16:27
|
|
Electronic signature
|
Oct 2, 2024, 16:32
|
|
|
Annexes to the contract
|
Oct 2, 2024, 16:28
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
внести зміни у п.6.1 розділу 6 договору
ID:
f3960ee3440848c9ad3ca785ff34b561
Date:
Dec 24, 2024, 17:27
Number of loaded document:
3
Date of signature:
Dec 24, 2024, 19:24
|
|
Electronic signature
|
Dec 24, 2024, 19:27
|
|
|
Annexes to the contract
|
Dec 24, 2024, 19:25
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внести зміни у Додатки 2 до Договору та викласти його у новій редакції
ID:
1358f6597cc740a682354713376f271c
Date:
Apr 2, 2025, 17:20
Number of loaded document:
4
Date of signature:
Apr 2, 2025, 17:19
|
|
Electronic signature
|
Apr 2, 2025, 17:20
|
|
|
Annexes to the contract
|
Apr 2, 2025, 17:19
|
|
|
Not indicated
|
Apr 2, 2025, 17:19
|
Change №5
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
внести зміни у п.2.1 Договору, Додатки №1, №3 до Договору та викласти їх у новій редакції.
ID:
dcdcef925d4142eca306db0647213c05
Date:
May 6, 2025, 10:53
Number of loaded document:
5
Date of signature:
May 6, 2025, 10:47
|
|
Electronic signature
|
May 6, 2025, 10:53
|
|
|
Not indicated
|
May 6, 2025, 10:51
|
|
|
Not indicated
|
May 6, 2025, 10:51
|
|
|
Not indicated
|
May 6, 2025, 10:51
|
|
|
Annexes to the contract
|
May 6, 2025, 10:51
|
Information about supplier
Name:
ТОВАРИСТВО З ОБМЕЖЕНОЮ ВІДПОВІДАЛЬНІСТЮ "СТРОЙЗАХИСТ"
EDRPOU code:
44386920
Website:
Not indicated
Address:
Україна, 01021, м. Київ, м. Київ, Кловський узвіз будинок 7 . .
Information about customer
Name:
УПРАВЛІННЯ КАПІТАЛЬНОГО БУДІВНИЦТВА МИКОЛАЇВСЬКОЇ МІСЬКОЇ РАДИ