Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
продовження терміну дії договору та внесення змін в календарний план
ID:
89a63e5595a14e2d9df343a32a905440
Date:
Dec 27, 2023, 11:42
Number of loaded document:
1
Date of signature:
Dec 27, 2023, 13:42
|
|
Electronic signature
|
Dec 27, 2023, 13:42
|
|
|
Schedule and stages
|
Dec 27, 2023, 13:41
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
продовження терміну дії договору та внесення змін в календарний план
ID:
3cd57db523b14143974bcb7c5bc37cdf
Date:
Mar 28, 2024, 07:11
Number of loaded document:
2
Date of signature:
Mar 28, 2024, 09:11
|
|
Electronic signature
|
Mar 28, 2024, 09:11
|
|
|
Annexes to the contract
|
Mar 28, 2024, 09:10
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
продовження терміну виконання робіт на доопрацювання розділів ПКД щодо влаштування слаботочних мереж (підстава лист виконавця від 26.06.2024 № 33)
ID:
b218176b99014b6eb840e4609ee84cd8
Date:
Jun 28, 2024, 11:00
Number of loaded document:
3
Date of signature:
Jun 28, 2024, 14:00
|
|
Electronic signature
|
Jun 28, 2024, 14:00
|
|
|
Annexes to the contract
|
Jun 28, 2024, 14:00
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
подовжено термін виконання робіт
ID:
7b91b25f55de469898b0689c7329dee7
Date:
Aug 2, 2024, 14:18
Number of loaded document:
4
Date of signature:
Jul 31, 2024, 23:59
|
|
Electronic signature
|
Aug 2, 2024, 14:18
|
|
|
Annexes to the contract
|
Aug 2, 2024, 14:18
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
подовження строку виконання робіт у звязку із зміною назви обєкта будівництва
ID:
2a5f4c698e84462ebb73a55c3c0a7bb5
Date:
Sep 4, 2024, 16:02
Number of loaded document:
5
Date of signature:
Aug 31, 2024, 23:59
|
|
Electronic signature
|
Sep 4, 2024, 16:02
|
|
|
Annexes to the contract
|
Sep 4, 2024, 15:58
|
Change №6
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
внесення змін назви обєкта будівництва
ID:
2679ccc793ec42238e6b255a09cd6b0e
Date:
Sep 26, 2024, 15:06
Number of loaded document:
6
Date of signature:
Sep 26, 2024, 15:06
|
|
Electronic signature
|
Sep 26, 2024, 15:05
|
|
|
Annexes to the contract
|
Sep 26, 2024, 15:01
|
Change №7
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
зміна класу наслідків відповідальності з СС2 на СС3
ID:
437ce644992047cd8c818f88547e2b00
Date:
Oct 15, 2024, 16:43
Number of loaded document:
7
Date of signature:
Oct 15, 2024, 16:43
|
|
Electronic signature
|
Oct 15, 2024, 16:42
|
|
|
Signed contract
|
Oct 15, 2024, 16:41
|
Information about supplier
Name:
Приватне підприємство "Проєкт-К"
EDRPOU code:
45404840
Website:
Not indicated
Address:
Україна, 25004, Кіровоградська область, м. Кропивницький, вул. Покровська, 50
Information about customer
Name:
КНП "ЦЕМД та МК у Кіровоградській області КОР"
EDRPOU code:
38540447
Website:
Not indicated
Address:
Україна, 25009, Кіровоградська область, КРОПИВНИЦЬКИЙ, м.Кропивницький, вул.Комарова, 56