Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Абзац 1 пункту 2.1 Договору у новій редакції. Строк виконання робіт: з дати підписання Договору по 30.04.2022 року. Абзац 1 пункту 3.1 Договору у новій редакції. Пункт 22.1 Договору у новій редакції. Договір набирає чинності з моменту підписання і діє по 30.04.2022 року, а в частині виконання грошових зобов’язань – до повного їх виконання. Додаток № 2 та Додаток № 3 у новій редакції.
ID:
1de649265cfd4d7b9536b51435a53ec1
Date:
Oct 12, 2021, 11:53
Number of loaded document:
1
Date of signature:
Oct 8, 2021, 00:00
|
|
Signed contract
|
Oct 12, 2021, 11:53
|
|
|
Electronic signature
|
Oct 12, 2021, 11:53
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Абзац перший пункту 3.1 Договору у новій редакції. Додаток № 2 та Додаток № 3 у новій редакції.
ID:
118b2631ab564b449a914a1509d6a61f
Date:
Dec 21, 2021, 10:47
Number of loaded document:
2
Date of signature:
Dec 20, 2021, 00:00
|
|
Signed contract
|
Dec 21, 2021, 10:47
|
|
|
Electronic signature
|
Dec 21, 2021, 10:47
|
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Абзац перший пункту 3.1 Договору у новій редакції. Додаток № 2 та Додаток № 3 у новій редакції.
ID:
a50eadf6073f40b7ba4abcf212202951
Date:
Dec 30, 2021, 17:24
Number of loaded document:
3
Date of signature:
Dec 29, 2021, 00:00
|
|
Electronic signature
|
Dec 30, 2021, 17:24
|
|
|
Signed contract
|
Dec 30, 2021, 17:24
|
Change №4
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Сторони засвідчують, що вартість робіт за Договором залишається незмінною. Додаток № 2 в новій редакції.
ID:
53eb2a56444c4247b7881b643f893e75
Date:
Feb 16, 2022, 18:07
Number of loaded document:
4
Date of signature:
Feb 16, 2022, 00:00
|
|
Electronic signature
|
Feb 16, 2022, 18:07
|
|
|
Signed contract
|
Feb 16, 2022, 18:07
|
Change №5
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Абзац 1 пункту 2.1 Договору у новій редакції. Строк виконання робіт: з дати підписання Договору по 31.08.2022 року. Пункт 22.1 Договору у новій редакції. Договір набирає чинності з моменту підписання і діє по 31.12.2022 року, а в частині виконання грошових зобов’язань – до повного їх виконання. Додаток № 2 у новій редакції.
ID:
4f0d6644514743899eb510adb04ea72e
Date:
Apr 20, 2022, 09:03
Number of loaded document:
5
Date of signature:
Apr 19, 2022, 00:00
|
|
Electronic signature
|
Apr 20, 2022, 09:03
|
|
|
Signed contract
|
Apr 20, 2022, 09:03
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Викласти п. 2.1, Додаток № 2 у новій редакції
ID:
68d87dc5924e439b9cbb0ac0a3b2b633
Date:
Sep 2, 2022, 08:20
Number of loaded document:
6
Date of signature:
Aug 30, 2022, 00:00
|
|
Signed contract
|
Sep 2, 2022, 08:20
|
|
|
Electronic signature
|
Sep 2, 2022, 08:20
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Керуючись пунктом 23.1 Договору про надання послуг з поточного середнього ремонту мосту на О 240204 /Шрамківка – ст. Драбів/ - Перервинці, км 0+700, через р. Чумгак, Золотоніський район, Черкаська область від 08.10.2021 № 291 (далі – Договір), пунктом 4 частини 5 статті 41 Закону України «Про публічні закупівлі», статтею 651 «Підстави для зміни або розірвання договору» Цивільного кодексу України, у зв’язку з продовженням строку дії воєнного стану в Україні згідно Указу Президента України від 7 листопада 2022 року № 757/2022 "Про продовження строку дії воєнного стану в Україні" та Закону України Про затвердження Указу Президента України "Про продовження строку дії воєнного стану в Україні" № 2738-IX від 16.11.2022, беручи до уваги лист Торгово-промислової палати України від 28.02.2022 р. № 2024/02.0-7.1 яким засвідчено настання форс-мажорних обставин (обставин непереборної сили), які є надзвичайними, невідворотними та об’єктивними і як наслідок зумовлюють неможливість виконати зобов’язання у попередньо погоджені Сторонами строки вирішили продовжити строк виконання робіт та дії Договору і у зв’язку з цим:
1. Абзац 1 пункту 2.1 Договору викласти у новій редакції:
Строк (термін) виконання робіт: з дати підписання Договору по 31.12.2023 року (згідно Календарного графіка – Додаток 2 до Договору).
2. Абзац 1 пункту 3.1 Договору викласти в новій редакції:
Ціна Договору визначається на підставі договірної ціни (Додаток 1 до Договору) і становить 3 436 790,03 грн. (Три мільйона чотириста тридцять шість тисяч сімсот дев’яносто гривень 03 копійки) з ПДВ, в т.ч. вартість робіт по Договору на 2021 рік становить 0 (нуль) грн.
вартість послуг по Договору на 2022 рік становить 0 (нуль) грн.
вартість послуг на Договору на 2023 рік становить 3 436 790,03 грн. з ПДВ.
3. Пункт 22.1 Договору викласти у новій редакції:
Цей Договір набирає чинності з моменту підписання і діє по 31.12.2023 року, а в частині виконання грошових зобов’язань - до повного їх виконання.
4. Додаток № 2 «Календарний графік» викласти у новій редакції. Додаток № 2 у новій редакції додається.
5. Додаток № 3 «План фінансування» викласти у новій редакції. Додаток № 3 у новій редакції додається.
ID:
8e3106dc9e8e4683825c3ec35c1a0f73
Date:
Dec 30, 2022, 09:28
Number of loaded document:
7
Date of signature:
Dec 28, 2022, 00:00
|
|
Electronic signature
|
Dec 30, 2022, 09:28
|
|
|
Signed contract
|
Dec 30, 2022, 09:28
|