Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання будівельно-монтажних робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 17.06.2018р. (включно).
ID:
f9653b4d3d4b450088a37211aff6f71a
Date:
May 21, 2018, 13:10
Number of loaded document:
09/02/2018-1
Date of signature:
May 21, 2018, 00:00
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання будівельно-монтажних робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 15.07.2018р. (включно).
ID:
6cf3a77db84e4ef099faad78c43c904a
Date:
Jun 18, 2018, 13:14
Number of loaded document:
09/02/2018-1
Date of signature:
Jun 18, 2018, 00:00
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання будівельно-монтажних робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 31.08.2018р. (включно).
ID:
8cc4814810594c3785455c94dee1724a
Date:
Jul 17, 2018, 15:57
Number of loaded document:
09/02/2018-1
Date of signature:
Jul 16, 2018, 00:00
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 30.09.2018р. (включно).
ID:
ca115e66fb30424682f9ec74da385d8e
Date:
Aug 31, 2018, 11:32
Number of loaded document:
09/02/2018-1
Date of signature:
Aug 31, 2018, 00:00
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 31.10.2018р. (включно).
ID:
15fab00cc65649b19620b6c2d963dff4
Date:
Sep 28, 2018, 09:36
Number of loaded document:
09/02/2018-1
Date of signature:
Sep 27, 2018, 00:00
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із продовженням строків виконання робіт з реконструкції по об’єкту, виникла необхідність продовження строків здійснення технічного нагляду під час проведення робіт до 10.11.2018р. (включно).
ID:
0f088b68723549d2912fc1eb9785c986
Date:
Oct 31, 2018, 13:23
Number of loaded document:
09/02/2018-1
Date of signature:
Oct 31, 2018, 00:00
Change №7
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Зменшення ціни договору до розміру 24291,37 грн. без ПДВ.
ID:
f4f40265d6884996954dde6764a9fe2a
Date:
Nov 9, 2018, 13:43
Number of loaded document:
09/02/2018-1
Date of signature:
Nov 9, 2018, 00:00