Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну виконання робіт
ID:
8a7f269748e54e64976b3dc8ffd9803e
Date:
Jun 30, 2017, 08:27
Number of loaded document:
1-17
Date of signature:
Jun 29, 2017, 08:27
|
|
Signed contract
|
Jun 30, 2017, 08:27
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну використання авансу та виконання робіт
ID:
bbc344d12e54460f9c51a0d7070ce526
Date:
Jul 20, 2017, 09:54
Number of loaded document:
1-17
Date of signature:
Jul 19, 2017, 09:53
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну виконання робіт
ID:
e30fab9c1c9f4051b341fd89826eaef2
Date:
Aug 15, 2017, 14:29
Number of loaded document:
1-17
Date of signature:
Aug 15, 2017, 14:28
|
|
Signed contract
|
Aug 15, 2017, 14:29
|
|
|
Signed contract
|
Jul 20, 2017, 09:54
|
Change №4
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну виконання робіт
ID:
25794d1d4df6473887e9692bf2767082
Date:
Sep 1, 2017, 09:59
Number of loaded document:
1-17
Date of signature:
Aug 31, 2017, 09:58
|
|
Signed contract
|
Sep 1, 2017, 09:58
|
Change №5
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну виконання робіт
ID:
f25fb158d97a4d248768b60151ae0381
Date:
Dec 20, 2017, 16:28
Number of loaded document:
1-17
Date of signature:
Dec 18, 2017, 00:00
|
|
Signed contract
|
Dec 20, 2017, 16:28
|
Change №6
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Уточнення порядку розрахунків
ID:
984e95f66f894f4897c9cd349e00034c
Date:
Dec 20, 2017, 16:35
Number of loaded document:
1-17
Date of signature:
Dec 20, 2017, 00:00
|
|
Signed contract
|
Dec 20, 2017, 16:35
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв'язку з відсутністю можливості виконати роботи у термін, визначений у договорі, термін дії договору продовжено до 31.03.2018. Уточнено вартість робіт у 2017 році
ID:
07c86c4eb79b4727bbbf310eb2408989
Date:
Dec 22, 2017, 10:24
Number of loaded document:
1-17
Date of signature:
Dec 21, 2017, 00:00
|
|
Signed contract
|
Dec 22, 2017, 10:24
|
Change №8
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору та строку виконання робіт до 30.04.2018
ID:
fa51057e5be24cccbf9f72f43fce62c1
Date:
Mar 30, 2018, 15:42
Number of loaded document:
1-17
Date of signature:
Mar 30, 2018, 00:00
|
|
Signed contract
|
Mar 30, 2018, 15:42
|
Change №9
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору та строку виконання робіт до 31.05.2018
ID:
792668a2a0db441991b3955ff5024a38
Date:
Apr 28, 2018, 08:18
Number of loaded document:
1-17
Date of signature:
Apr 27, 2018, 00:00
|
|
Signed contract
|
Apr 28, 2018, 08:18
|
Change №10
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору та строку виконання робіт до 30.06.2018
ID:
84af72ba64204d198b5f9fde774de9f8
Date:
Jun 1, 2018, 15:14
Number of loaded document:
1-17
Date of signature:
May 30, 2018, 00:00
|
|
Signed contract
|
Jun 1, 2018, 15:14
|
Change №11
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору та строку виконання робіт до 31.07.2018
ID:
16009adcdc344a2ebab55a2bc31fa71c
Date:
Jun 27, 2018, 10:20
Number of loaded document:
1-17
Date of signature:
Jun 25, 2018, 00:00
|
|
Signed contract
|
Jun 27, 2018, 10:20
|
Change №12
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Відновлення фінансування у 2018 році
ID:
fd1f54cb8bda4f089930fd6adc925f9a
Date:
Jul 20, 2018, 16:12
Number of loaded document:
1-17
Date of signature:
Jul 19, 2018, 00:00
|
|
Signed contract
|
Jul 20, 2018, 16:12
|