Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
зміна реквізитів
ID:
48aca0f9b8a04a929c8217a66de1f1cd
Date:
Oct 23, 2019, 18:32
Number of loaded document:
1
Date of signature:
Oct 23, 2019, 00:00
|
|
Annexes to the contract
|
Oct 23, 2019, 18:32
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
зміни до плану фінансування будівництва
ID:
059bc6aea40d4ddfb1e65b38927ac3e7
Date:
Dec 17, 2019, 15:09
Number of loaded document:
2
Date of signature:
Dec 16, 2019, 00:00
|
|
Annexes to the contract
|
Dec 17, 2019, 15:09
|
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
відповідно до обсягу вартості фактично виконаних робіт, зменшити виділені кошти
ID:
79d4382da21a4c7cb9d9c4eb46e65111
Date:
Dec 28, 2019, 17:29
Number of loaded document:
3
Date of signature:
Dec 27, 2019, 00:00
|
|
Not indicated
|
Dec 28, 2019, 17:28
|
Change №4
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна реквізитів та плану фінансування
ID:
a8e3e1f31da345ea8d7414dcc75bc8ba
Date:
Jun 5, 2020, 16:34
Number of loaded document:
№4
Date of signature:
Jun 5, 2020, 00:00
|
|
Annexes to the contract
|
Jun 5, 2020, 16:34
|
Change №5
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна плану фінансування
ID:
245ca6519f024914a2516222ebe2abd0
Date:
Dec 16, 2020, 16:44
Number of loaded document:
5
Date of signature:
Dec 16, 2020, 00:00
|
|
Annexes to the contract
|
Dec 16, 2020, 16:40
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
зміни до плану фінансування та продовження строку дії договору
ID:
33f0ca93425143ee85805087e6a59bf6
Date:
Jun 23, 2021, 16:59
Number of loaded document:
6
Date of signature:
Jun 23, 2021, 00:00
|
|
Annexes to the contract
|
Jun 23, 2021, 16:59
|
Change №7
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
зміни до плану фінансування
ID:
06e8fabe344f4583b4668883bb65b9ca
Date:
Dec 29, 2021, 21:12
Number of loaded document:
7
Date of signature:
Dec 29, 2021, 00:00
|
|
Annexes to the contract
|
Dec 29, 2021, 21:12
|
Change №8
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань щодо передання товару, виконання робіт, надання послуг (через документально підтверджені об’єктивні обставини)
ID:
da1d3d165e2e4e7bb93d7d2ea7f6fe0b
Date:
Dec 29, 2022, 15:47
Number of loaded document:
8
Date of signature:
Dec 29, 2022, 00:00
|
|
Annexes to the contract
|
Dec 29, 2022, 15:47
|
Change №9
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна реквізитів
ID:
167dc73ac2c743e1a56dbcbda8ecf805
Date:
Feb 8, 2023, 12:20
Number of loaded document:
9
Date of signature:
Feb 8, 2023, 00:00
|
|
Annexes to the contract
|
Feb 8, 2023, 12:20
|
Change №10
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Change of conditions due to extension of the contract term, sufficient for conducting procurement procedure at the beginning of the next year, in the amount not exceeding 20% of the amount specified in the contract made in the previous year, if expenses for these purposes are approved in the established order
Note:
Продовження строку виконання договору та зміна плану фінансування
ID:
2d4b7310e44d4e16bd227fc732448dbd
Date:
Sep 25, 2023, 16:08
Number of loaded document:
10
Date of signature:
Sep 25, 2023, 00:00
|
|
Annexes to the contract
|
Sep 25, 2023, 16:08
|
Change №11
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна реквізитів
ID:
ce45ff302a6142f790adb86fe4f7734d
Date:
Dec 19, 2023, 12:08
Number of loaded document:
11
Date of signature:
Dec 18, 2023, 00:00
|
|
Annexes to the contract
|
Dec 19, 2023, 12:08
|
Change №12
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна плану фінансування
ID:
9618760c85644ce290210e3859ddabf9
Date:
Dec 29, 2023, 16:28
Number of loaded document:
12
Date of signature:
Dec 29, 2023, 00:00
|
|
Annexes to the contract
|
Dec 29, 2023, 16:28
|