Проведення проектно-вишукувальних робіт по об'єкту: «Капітальний ремонт вул. Б. Лятошинського в м. Житомирі»
Valid:
Jan 5, 2021 – Dec 31, 2023
Contract ID :
UA-2020-12-07-006788-c-c1
Number:
3
Date of signature:
Jan 5, 2021, 11:25
Items list
| Name | Quantity | Delivery period | Place of delivery |
|---|---|---|---|
|
Name: Проведення проектно-вишукувальних робіт по об'єкту: «Капітальний ремонт вул. Б. Лятошинського в м. Житомирі»
Code DK 021:2015:
71320000-7 Послуги з інженерного проектування
|
Quantity: 1 роботи |
Delivery period: Dec 21, 2020, 00:00 – Dec 31, 2022, 00:00 |
Place of delivery: Україна, 10014, Житомирська область, Житомир, Б. Лятошинського |
Procurement documents
| Document name | Document type | Date of publishing |
| Signed contract | Jan 6, 2021, 11:26 | |
| Electronic signature | Jan 6, 2021, 11:27 | |
| Electronic signature | Jan 6, 2021, 11:27 | |
| Change history | ||
Changes to contract
Change №1
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Нова редакція п. 1.2. та додатка № 2 договору
ID:
d2e2020862c34062a85f7c9b0cbfa984
Date:
Apr 12, 2021, 16:36
Number of loaded document:
1
Date of signature:
Apr 12, 2021, 16:33
| Document name | Document type | Date of publishing |
| Electronic signature | Apr 12, 2021, 16:36 | |
| Annexes to the contract | Apr 12, 2021, 16:34 |
Change №2
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Нова редакція п. 1.2. та додатка № 2 договору
ID:
5d30e6266a9842218d544e2768e7e450
Date:
Oct 4, 2021, 14:29
Number of loaded document:
2
Date of signature:
Oct 4, 2021, 14:28
| Document name | Document type | Date of publishing |
| Electronic signature | Oct 4, 2021, 14:29 | |
| Annexes to the contract | Oct 4, 2021, 14:28 |
Change №3
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Нова редакція п. 1.2., п.2.1., п.11.1., додаток № 2 договору
ID:
ff5fda76e72549279be109103a006ea1
Date:
Dec 28, 2021, 11:59
Number of loaded document:
3
Date of signature:
Dec 28, 2021, 11:54
| Document name | Document type | Date of publishing |
| Annexes to the contract | Dec 28, 2021, 11:58 | |
| Electronic signature | Dec 28, 2021, 11:59 |
Change №4
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Нова редакція п. 1.2.та додатка № 2 договору
ID:
958e4022ed704a498aa8a9aaf264f5a6
Date:
May 16, 2022, 16:59
Number of loaded document:
4
Date of signature:
May 13, 2022, 16:58
| Document name | Document type | Date of publishing |
| Electronic signature | May 16, 2022, 16:59 | |
| Annexes to the contract | May 16, 2022, 16:59 |
Change №5
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Нова редакція п. 1.2., п. 2.1. та додатка № 2 договору
ID:
10c999ff6cbe4b269572445977343fe2
Date:
Aug 16, 2022, 10:23
Number of loaded document:
5
Date of signature:
Aug 16, 2022, 10:19
| Document name | Document type | Date of publishing |
| Annexes to the contract | Aug 16, 2022, 10:21 | |
| Electronic signature | Aug 16, 2022, 10:23 |
Change №6
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Прийняття в новій редакції п. 2.1. та 11.1. договору у зв'язку із змінами умов фінансування
ID:
f7a224d0640d4b45811332cf87e713df
Date:
Dec 23, 2022, 11:53
Number of loaded document:
6
Date of signature:
Dec 22, 2022, 11:49
| Document name | Document type | Date of publishing |
| Electronic signature | Dec 23, 2022, 11:53 | |
| Annexes to the contract | Dec 23, 2022, 11:51 |
Change №7
Status:
Confirmed
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Прийняття в новій редакції п. 2.1. договору у зв'язку з виділенням фінансування
ID:
39fc5b7f85e24645a8b53b4b29d2fdd5
Date:
Mar 2, 2023, 13:47
Number of loaded document:
7
Date of signature:
Mar 2, 2023, 13:37
| Document name | Document type | Date of publishing |
| Electronic signature | Mar 2, 2023, 13:47 | |
| Annexes to the contract | Mar 2, 2023, 13:45 |
Main contact
Information about supplier
Name:
ФОП "ПОСЛАВСЬКИЙ ОЛЕКСАНДР АНАТОЛІЙОВИЧ"
EDRPOU code:
2926808010
Website:
Not indicated
Address:
Україна, 10024, Житомирська область, місто Житомир, ПРОЇЗД АКАДЕМІКА ТУТКОВСЬКОГО, будинок 12, квартира 69
Information about customer
Name:
Управління капітального будівництва Житомирської міської ради
EDRPOU code:
36072499
Website:
Not indicated
Address:
Україна, 10014, Житомирська область, м.Житомир, МАЙДАН ІМ. С.П.КОРОЛЬОВА, 4/2