Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно додаткової угоди
ID:
1635fc6b905143fdb9e3c911f0d48a52
Date:
Apr 30, 11:09
Number of loaded document:
1
Date of signature:
Apr 30, 00:00
|
|
Annexes to the contract
|
Apr 30, 14:08
|
|
|
Electronic signature
|
Apr 30, 14:09
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно додаткової угоди (продовження термінів виконання робіт)
ID:
bf29b82dde5f4ec38cca0f0e10bd0aa6
Date:
May 26, 13:19
Number of loaded document:
2
Date of signature:
May 15, 00:00
|
|
Annexes to the contract
|
May 26, 16:18
|
|
|
Electronic signature
|
May 26, 16:19
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно додаткової угоди (продовження строку виконання робіт)
ID:
b9a099eff8314f799491458c5f73b5ad
Date:
Jun 18, 12:52
Number of loaded document:
3
Date of signature:
Jun 15, 00:00
|
|
Electronic signature
|
Jun 18, 15:52
|
|
|
Annexes to the contract
|
Jun 18, 15:52
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно додаткової угоди (продовження строків виконання робіт)
ID:
2e3c5766cf214be388e8311b4f2f4068
Date:
Jul 16, 11:10
Number of loaded document:
4
Date of signature:
Jul 15, 00:00
|
|
Electronic signature
|
Jul 16, 11:10
|
|
|
Annexes to the contract
|
Jul 16, 11:09
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно додаткової угоди (
ID:
ebea05d62e564805be21fb9dc918c2cb
Date:
Aug 18, 12:13
Number of loaded document:
5
Date of signature:
Aug 14, 00:00
|
|
Electronic signature
|
Aug 18, 12:13
|
|
|
Annexes to the contract
|
Aug 18, 12:13
|
Information about supplier
Name:
ТОВАРИСТВО З ОБМЕЖЕНОЮ ВІДПОВІДАЛЬНІСТЮ "В.С. ПРОЕКТ"
EDRPOU code:
35931274
Website:
Not indicated
Address:
Україна, 65009, Одеська область, Одеса, ПРОВУЛОК СВІТЛИЙ, будинок 3
Information about customer
Name:
Чорноморська селищна рада Одеського району Одеської області
EDRPOU code:
05583176
Website:
Not indicated
Address:
Україна, 67570, Одеська область, Одеський р-н, селище Чорноморське, вулиця Захисників України, будинок 19