Реконструкція системи теплопостачання виробничої бази будівельно-монтажної фірми "УКРГАЗПРОМБУД" в м. Полтава, вул.Ковалівська, 9"
Valid:
Sep 28, 2016 – Sep 28, 2018
Contract ID :
UA-2016-08-22-000462-c-b1
Number:
124
Date of signature:
Sep 28, 2016, 00:00
Items list
| Name | Quantity | Delivery period | Place of delivery |
|---|---|---|---|
|
Name: Реконструкція системи теплопостачання виробничої бази будівельно-монтажної фірми "УКРГАЗПРОМБУД" в м. Полтава, вул.Ковалівська, 9" (Будівельні роботи)
Code DK 021:2015:
45000000-7 Будівельні роботи
Code:
000 Не визначений
|
Quantity: 1 Работы |
Delivery period: Dec 29, 2017, 00:00 |
Place of delivery: Україна, 36015, Полтавська обл., Полтава, Ковалівська,9 |
Procurement documents
| Document name | Document type | Date of publishing |
| Electronic signature | Oct 4, 2016, 12:11 | |
| Electronic signature | Oct 4, 2016, 12:11 | |
| Electronic signature | Oct 4, 2016, 12:11 | |
|
|
||
| Signed contract | Sep 29, 2016, 10:43 | |
| Electronic signature | Sep 29, 2016, 10:43 | |
| Not indicated | Sep 28, 2018, 09:33 | |
Changes to contract
Change №1
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
І етап будівництва: Поставка, монтаж, пусконалагоджувальні роботи з введенням в експлуатацію котельного обладнання до 01.11.2016 р.
ID:
4db757e6ce1b4173a81d79b775e311cc
Date:
Oct 10, 2016, 10:59
Number of loaded document:
124
| Document name | Document type | Date of publishing |
| Not indicated | Oct 10, 2016, 10:58 |
Change №2
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Змінено термін (строк) виконання робіт та календарний план на будівництво
ID:
0e78675af4d240b49838202a6bca5203
Date:
Oct 20, 2017, 15:13
Number of loaded document:
124
Date of signature:
Oct 20, 2017, 00:00
| Document name | Document type | Date of publishing |
| Electronic signature | Oct 20, 2017, 15:12 | |
| Not indicated | Oct 20, 2017, 15:09 | |
| Not indicated | Oct 20, 2017, 15:09 |
Change №3
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Змінено термін (строк) виконання робіт та календарний план на будівництво
ID:
458ba2ea7f2c4a568472f50f3b6a8a18
Date:
Nov 23, 2017, 10:17
Number of loaded document:
124
Date of signature:
Nov 22, 2017, 00:00
| Document name | Document type | Date of publishing |
| Electronic signature | Nov 23, 2017, 10:17 | |
| Not indicated | Nov 23, 2017, 10:14 | |
| Not indicated | Nov 23, 2017, 10:14 |
Main contact
Information about supplier
Name:
ООО "ГК "Термоінжиніринг""
EDRPOU code:
39395692
Website:
Address:
Украина, 01021, Киев, Киев, ул. Институтская, 16, оф.1/3
Information about customer
Name:
Філія "БМФ "УКРГАЗПРОМБУД" ПАТ "УКРТРАНСГАЗ"
EDRPOU code:
00156630
Website:
Not indicated
Address:
Україна, 36004, Полтавська обл., Полтава, м. Полтава, вул. Кагамлика, 33-а