Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору
ID:
0e77d5a94da147d08ed9d7d9ee217084
Date:
Dec 21, 2020, 20:22
Number of loaded document:
1
Date of signature:
Dec 21, 2020, 00:00
|
|
Not indicated
|
Dec 21, 2020, 20:22
|
|
|
Electronic signature
|
Dec 21, 2020, 20:22
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору з документально підтверджених обставин
ID:
3fc0862d93fc45d8a8dfc949089d52a4
Date:
Mar 26, 2021, 09:56
Number of loaded document:
2
Date of signature:
Mar 25, 2021, 00:00
|
|
Not indicated
|
Mar 26, 2021, 09:55
|
|
|
Electronic signature
|
Mar 26, 2021, 09:56
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору
ID:
e240856897c44359bc80ed00230c75bd
Date:
Jun 30, 2021, 09:09
Number of loaded document:
3
Date of signature:
Jun 30, 2021, 00:00
|
|
Electronic signature
|
Jun 30, 2021, 09:08
|
|
|
Not indicated
|
Jun 30, 2021, 09:07
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору у звязку з затримкою фінансування витрат Замовника
ID:
767211932ba648f797079e88f512f653
Date:
Jul 29, 2021, 17:04
Number of loaded document:
4
Date of signature:
Jul 29, 2021, 00:00
|
|
Not indicated
|
Jul 29, 2021, 17:04
|
|
|
Electronic signature
|
Jul 29, 2021, 17:04
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору у звязку з затримкою фінансування витрат Замовника
ID:
98af1c2004d1427097eae9bb46bd8104
Date:
Aug 30, 2021, 15:09
Number of loaded document:
5
Date of signature:
Aug 30, 2021, 00:00
|
|
Electronic signature
|
Aug 30, 2021, 15:09
|
|
|
Signed contract
|
Aug 30, 2021, 15:09
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору у звязку з затримкою фінансування витрат Замовника
ID:
61019e78c77c464b967d7ff03a6298b6
Date:
Aug 30, 2021, 15:23
Number of loaded document:
5.
Date of signature:
Aug 30, 2021, 00:00
|
|
Signed contract
|
Aug 30, 2021, 15:23
|
|
|
Electronic signature
|
Aug 30, 2021, 15:23
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору у зв'язку з затримкою фінансування витрат замовника
ID:
b951899b60884196ab79283749351a3b
Date:
Sep 30, 2021, 14:22
Number of loaded document:
6
Date of signature:
Sep 30, 2021, 00:00
|
|
Electronic signature
|
Sep 30, 2021, 14:22
|
|
|
Signed contract
|
Sep 30, 2021, 14:21
|
Information about supplier
Name:
товариство з обмеженою відповідальністю "Експерт Проект Плюс"
EDRPOU code:
41041331
Website:
Not indicated
Address:
Україна, 46008, Тернопільська область, Тернопіль, Микулинецька, 3А офіс 214
Information about customer
Name:
СЛУЖБА АВТОМОБІЛЬНИХ ДОРІГ У ТЕРНОПІЛЬСЬКІЙ ОБЛАСТІ
EDRPOU code:
25887079
Website:
Not indicated
Address:
Україна, 46001, Тернопільська область, Тернопіль, ВУЛИЦЯ О. КУЛЬЧИЦЬКОЇ, будинок 8