Продовжили термін виконання та термін дії договору

Valid:
Aug 19, 2016 – Dec 31, 2016
Contract ID :
UA-2016-07-08-000118-a-a1
Number:
1608000453
Date of signature:
Aug 19, 2016, 00:00

Items list

Name Quantity Delivery period Place of delivery

Name:

Реконструкція системи теплопостачання проммайданчика компресорної станції «Голятин» (Будівельні роботи)

Code DK 021:2015: 45000000-7 Будівельні роботи
Code: 000 Не визначений

Quantity:

1 Работы

Delivery period:

Dec 31, 2016, 00:00

Place of delivery:

Україна, 89100, Закарпатська обл., смт. Воловець, КС Голятин

Procurement documents

Document name Document type Date of publishing
Electronic signature Dec 19, 2016, 16:21
Electronic signature Dec 19, 2016, 16:21
Signed contract Aug 19, 2016, 14:58
Changes to contract

Change №1

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Протокол технічної наради щодо виконання робіт по обєкту "Реконструкція системи теплопостачання проммайданчика компресорної станції "Голятин" від 07.12.2016, продовження терміну будівництва до 31.07.2017
ID:
f9731c06c2074a2f9735a7e82f858df1
Date:
Dec 19, 2016, 16:21
Number of loaded document:
1608000453
Date of signature:
Dec 19, 2016, 00:00
Document name Document type Date of publishing
Not indicated Dec 19, 2016, 16:20
Not indicated Dec 19, 2016, 16:19

Change №2

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Протокол Технічної наради від 07.07.2017 №б/н , продовження терміну виконання робіт та терміну дії договору
ID:
9d031532cb0648ce966773d55ccaa464
Date:
Aug 4, 2017, 12:08
Number of loaded document:
1608000453
Date of signature:
Jul 31, 2017, 00:00
Document name Document type Date of publishing
Not indicated Aug 4, 2017, 12:07
Electronic signature Aug 4, 2017, 12:08

Change №3

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії виконання договору
ID:
1073e6cf9ffc47cca0c866708607dba3
Date:
Sep 26, 2017, 12:39
Number of loaded document:
1608000453
Date of signature:
Sep 26, 2017, 00:00
Document name Document type Date of publishing
Not indicated Sep 26, 2017, 12:38
Electronic signature Sep 26, 2017, 12:38
Main contact
Name:
Юрій Ч.
Phone:
+380342784302
E-mail:
Fax:
Information about supplier
Name:
ООО "ФІРМА КАЛИНА ІФ"
EDRPOU code:
13664090
Website:
Not indicated
Address:
Украина, 76018, Івано-Франківська область, м. Івано-Франківськ, вул. А. Мельника, 1-А
Information about customer
Name:
Філія "УМГ "ПРИКАРПАТТРАНСГАЗ" ПАТ "УКРТРАНСГАЗ"
EDRPOU code:
00153133
Website:
Not indicated
Address:
Україна, 76018, Івано-Франківська обл., Івано-Франківськ, м.Івано-Франківськ, вул. Незалежності, 48