ДСТУ Б.Д.1.1-1:2013 (ДК021-2015: 45454000-4 — Реконструкція) Енергоблок №3. Модернізація нейтронних аналізаторів НАР-Б, концентратомірів НАР-12. ПКД

Valid:
Dec 31, 2020
Contract ID :
UA-2018-10-05-002518-c-c1
Number:
2-123-08-18-04731
Date of signature:
Oct 5, 2018, 00:00

Items list

Name Quantity Delivery period Place of delivery

Name:

ДСТУ Б.Д.1.1-1:2013 (ДК021-2015: 45454000-4 — Реконструкція) Енергоблок №3. Модернізація нейтронних аналізаторів НАР-Б, концентратомірів НАР-12. ПКД

Code DK 021:2015: 45454000-4 Реконструкція

Quantity:

1 роботи

Delivery period:

Dec 31, 2018, 00:00

Place of delivery:

Україна, 55001, Миколаївська область, Южноукраїнськ, промзона

Procurement documents

Document name Document type Date of publishing
Electronic signature Oct 5, 2018, 16:00
Electronic signature Oct 5, 2018, 16:00
Signed contract Oct 5, 2018, 16:00
Changes to contract

Change №1

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Внесення змін у календарний план, збільшення вартості
ID:
e34bb0058c1843b091613bc8b4755339
Date:
Jun 27, 2019, 11:55
Number of loaded document:
2-123-08-18-04731
Date of signature:
Jun 26, 2019, 00:00
Document name Document type Date of publishing
Annexes to the contract Jun 27, 2019, 11:53
Electronic signature Jun 27, 2019, 11:54

Change №2

Status:
Confirmed
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Change of conditions due to extension of the contract term, sufficient for conducting procurement procedure at the beginning of the next year, in the amount not exceeding 20% of the amount specified in the contract made in the previous year, if expenses for these purposes are approved in the established order
Note:
Внесення змін в календарний план
ID:
e7c43b0a586748e699cff9d36fbfb5a6
Date:
Sep 5, 2019, 11:12
Number of loaded document:
№2 до договору 8191-18-07/2-123-08-18-04731
Date of signature:
Sep 5, 2019, 00:00
Document name Document type Date of publishing
Annexes to the contract Sep 5, 2019, 11:10
Electronic signature Sep 5, 2019, 11:11

Change №3

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесення змін в календарний план
ID:
7e3f7370c4b741439dfa1fdb737278a5
Date:
Feb 21, 2020, 16:06
Number of loaded document:
3/2-123-08-18-04731
Date of signature:
Feb 21, 2020, 00:00
Document name Document type Date of publishing
Annexes to the contract Feb 21, 2020, 16:05
Electronic signature Feb 21, 2020, 16:06
Main contact
Name:
Гурьянова Ирина Викторовна
Phone:
380513642286
E-mail:
Fax:
0513642412
Information about supplier
Name:
АТ ХНДтаПКІ «Енергопроект»
EDRPOU code:
14078902
Website:
Not indicated
Address:
Україна, 61003, Харківська область, Харків, Московський пр.10/12
Information about customer
Name:
ВП ЮУАЕС ДП НАЕК «Енергоатом»
EDRPOU code:
20915546
Website:
Address:
Україна, 55000, Миколаївська область, Южноукраїнськ, Миколаївської обл., м. Южноукраїнськ