Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Фінансування в 2021 році виділено не повному обсязі
ID:
fac90b7dd47e4c7dbfa18707b62cce82
Date:
Dec 30, 2021, 08:56
Number of loaded document:
№3
Date of signature:
Dec 30, 2021, 00:00
|
|
Annexes to the contract
|
Dec 30, 2021, 08:56
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Листом від 28.02.2022 № 2024/02.2-7.1 Торгово-промисловою палатою України засвідчені та підтверджені форс-мажорні обставини (обставини непереборної сили) - військова агресія Російської Федерації проти України з 24 лютого 2022, які до її офіційного закінчення є надзвичайними, невідворотними та об’єктивними обставинами для суб’єктів господарської діяльності по Договору. Внаслідок наростання цих форс-мажорних обставин стало неможливим виконання зобов’язань у встановлений термін, згідно зазначеного Договору.
ID:
ad7814928ce94e89969e273b598a2d89
Date:
Dec 28, 2022, 09:20
Number of loaded document:
№4
Date of signature:
Dec 28, 2022, 00:00
|
|
Annexes to the contract
|
Dec 28, 2022, 09:20
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Листом від 28.02.2022 № 2024/02.2-7.1 Торгово-промисловою палатою України засвідчені та підтверджені форс-мажорні обставини (обставини непереборної сили) - військова агресія Російської Федерації проти України з 24 лютого 2022, які до її офіційного закінчення є надзвичайними, невідворотними та об’єктивними обставинами для суб’єктів господарської діяльності по Договору. Внаслідок наростання цих форс-мажорних обставин стало неможливим виконання зобов’язань у встановлений термін, згідно зазначеного Договору
ID:
c54f3c96be0640c986b222639228a8c1
Date:
Dec 26, 2023, 07:33
Number of loaded document:
№5
Date of signature:
Dec 25, 2023, 00:00
|
|
Annexes to the contract
|
Dec 26, 2023, 09:33
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Листом від 28.02.2022 № 2024/02.2-7.1 Торгово-промисловою палатою України засвідчені та підтверджені форс-мажорні обставини (обставини непереборної сили) - військова агресія Російської Федерації проти України з 24 лютого 2022, які до її офіційного закінчення є надзвичайними, невідворотними та об’єктивними обставинами для суб’єктів господарської діяльності по Договору. Внаслідок наростання цих форс-мажорних обставин стало неможливим виконання зобов’язань у встановлений термін, згідно зазначеного Договору
ID:
16ecc1bcd446492e8a6bdd6397eff78d
Date:
Dec 24, 2024, 15:17
Number of loaded document:
№6
Date of signature:
Dec 24, 2024, 00:00
|
|
Annexes to the contract
|
Dec 24, 2024, 15:17
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Листом від 28.02.2022 № 2024/02.2-7.1 Торгово-промисловою палатою України засвідчені та підтверджені форс-мажорні обставини (обставини непереборної сили) - військова агресія Російської Федерації проти України з 24 лютого 2022, які до її офіційного закінчення є надзвичайними, невідворотними та об’єктивними обставинами для суб’єктів господарської діяльності по Договору. Внаслідок наростання цих форс-мажорних обставин стало неможливим виконання зобов’язань у встановлений термін, згідно зазначеного Договору
ID:
5c71cc9ae4364316a6a3c4bb58f4e2b7
Date:
Dec 31, 2025, 09:09
Number of loaded document:
№7
Date of signature:
Dec 31, 2025, 00:00
|
|
Annexes to the contract
|
Dec 31, 2025, 09:09
|
Information about customer
Name:
Комунальне підприємство "Дніпровський електротранспорт" Дніпровської міської ради
EDRPOU code:
32616520
Website:
Not indicated
Address:
Україна, 49038, Дніпропетровська область, Дніпро, Проспект Дмитра Яворницького, 119а