Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
300a566bf9864e53b7c57a0727ebb9c2
Date:
Apr 8, 2019, 16:26
Number of loaded document:
538
Date of signature:
Apr 8, 2019, 16:00
|
|
Electronic signature
|
Apr 8, 2019, 16:26
|
|
|
Annexes to the contract
|
Apr 8, 2019, 16:17
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
63cf73a1ca6f47d1b111c9cc6a957089
Date:
Jun 24, 2019, 17:26
Number of loaded document:
538
Date of signature:
Jun 24, 2019, 15:00
|
|
Annexes to the contract
|
Jun 24, 2019, 17:25
|
|
|
Electronic signature
|
Jun 24, 2019, 17:26
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань, Покращення якості предмета закупівлі
ID:
7a0b71e2aea6406b852feb73b936bf3f
Date:
Jul 16, 2019, 13:58
Number of loaded document:
3
Date of signature:
Jul 15, 2019, 11:00
|
|
Annexes to the contract
|
Jul 16, 2019, 13:57
|
|
|
Electronic signature
|
Jul 16, 2019, 13:58
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
e460aa237cfa4326b19f88e7c97721d1
Date:
Sep 2, 2019, 16:35
Number of loaded document:
4
Date of signature:
Aug 30, 2019, 16:40
|
|
Electronic signature
|
Sep 2, 2019, 16:35
|
|
|
Annexes to the contract
|
Sep 2, 2019, 16:34
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
4d716d0dacad4a10a44f0a41a90ef29a
Date:
Oct 1, 2019, 11:23
Number of loaded document:
5
Date of signature:
Sep 30, 2019, 11:20
|
|
Electronic signature
|
Oct 1, 2019, 11:23
|
|
|
Annexes to the contract
|
Oct 1, 2019, 11:22
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
d6a6ba8e4b8b4dc9b886c4aa8ecf8c0a
Date:
Nov 1, 2019, 18:32
Number of loaded document:
6
Date of signature:
Oct 31, 2019, 17:00
|
|
Electronic signature
|
Nov 1, 2019, 18:32
|
|
|
Annexes to the contract
|
Nov 1, 2019, 18:31
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та виконання зобов’язань
ID:
68fd55d7c3d24d0e9f67e51239c04230
Date:
Dec 3, 2019, 10:24
Number of loaded document:
7
Date of signature:
Dec 2, 2019, 12:00
|
|
Annexes to the contract
|
Dec 3, 2019, 10:21
|
|
|
Electronic signature
|
Dec 3, 2019, 10:24
|
|
|
Annexes to the contract
|
Dec 3, 2019, 10:21
|