Капітальний ремонт басейну у СЗШ № 72 на вул. Зубрівській, 1 у м. Львові

Valid:
Nov 4, 2019 – Jun 25, 2025
Contract ID :
UA-2019-09-06-001432-a-b1
Number:
500-к
Date of signature:
Nov 4, 2019, 10:00

Items list

Name Quantity Delivery period Place of delivery

Name:

Капітальний ремонт басейну у СЗШ № 72 на вул. Зубрівській, 1 у м. Львові

Code DK 021:2015: 45453000-7 Капітальний ремонт і реставрація

Quantity:

1 роботи

Delivery period:

Dec 31, 2019, 02:00

Place of delivery:

Україна, 79066, Львівська область, Львів, вул. Зубрівська, 1

Procurement documents

Document name Document type Date of publishing
Electronic signature Jun 26, 2025, 12:11
Annexes to the contract Jun 26, 2025, 12:10
Signed contract Nov 4, 2019, 15:14
Annexes to the contract Nov 4, 2019, 15:14
Electronic signature Nov 4, 2019, 15:21
Changes to contract

Change №1

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
уточнення порядку фінансування робіт у 2019 році.
ID:
312c616437dc47ebbe2fc528140588fc
Date:
Nov 7, 2019, 15:56
Number of loaded document:
1
Date of signature:
Nov 6, 2019, 17:00
Document name Document type Date of publishing
Nov 7, 2019, 15:54
Electronic signature Nov 7, 2019, 15:56

Change №2

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт у 2020 році.
ID:
bc70b7d2610a46908d6d46e714b5dece
Date:
Dec 22, 2020, 12:19
Number of loaded document:
3
Date of signature:
Dec 21, 2020, 16:00
Document name Document type Date of publishing
Annexes to the contract Dec 22, 2020, 12:18
Electronic signature Dec 22, 2020, 12:19

Change №3

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт у 2020 році.
ID:
6964e6cd0dbc4a669c8aefeeb9c06c79
Date:
Dec 22, 2020, 12:22
Number of loaded document:
4
Date of signature:
Dec 22, 2020, 11:49
Document name Document type Date of publishing
Electronic signature Dec 22, 2020, 12:21
Annexes to the contract Dec 22, 2020, 12:21

Change №4

Status:
Confirmed
Change cause:
Change of conditions due to extension of the contract term, sufficient for conducting procurement procedure at the beginning of the next year, in the amount not exceeding 20% of the amount specified in the contract made in the previous year, if expenses for these purposes are approved in the established order
Note:
Продовження строку дії договору на наступний рік
ID:
5d81dbecd17a42429c2731411b544b9b
Date:
Jan 13, 2021, 14:04
Number of loaded document:
5
Date of signature:
Jan 13, 2021, 12:00
Document name Document type Date of publishing
Annexes to the contract Jan 13, 2021, 14:02
Electronic signature Jan 13, 2021, 14:04

Change №5

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт у 2021 році.
ID:
f7aa5acb5ceb4eeeb220376025e00b81
Date:
Mar 31, 2021, 13:41
Number of loaded document:
6
Date of signature:
Mar 31, 2021, 13:00
Document name Document type Date of publishing
Annexes to the contract Mar 31, 2021, 13:40
Electronic signature Mar 31, 2021, 13:41

Change №6

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт.
ID:
0a623011fbee42c8b75dbaff0dabcb76
Date:
Dec 20, 2021, 15:07
Number of loaded document:
7
Date of signature:
Dec 17, 2021, 17:00
Document name Document type Date of publishing
Annexes to the contract Dec 20, 2021, 15:03
Electronic signature Dec 20, 2021, 15:06

Change №7

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт.
ID:
e3673f6883284a90a419e9f33d452efa
Date:
Mar 11, 2022, 16:32
Number of loaded document:
8
Date of signature:
Mar 10, 2022, 17:00
Document name Document type Date of publishing
Electronic signature Mar 11, 2022, 16:32
Annexes to the contract Mar 11, 2022, 14:00

Change №8

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та зміна реквізитів
ID:
d6d00c91841649fda2f91fcf42e1edb0
Date:
Dec 26, 2022, 13:37
Number of loaded document:
9
Date of signature:
Dec 26, 2022, 10:10
Document name Document type Date of publishing
Annexes to the contract Dec 26, 2022, 13:35
Electronic signature Dec 26, 2022, 13:36

Change №9

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт
ID:
6fad48c39a4142f3b9280723aea6c868
Date:
Jan 4, 2023, 13:03
Number of loaded document:
10
Date of signature:
Dec 30, 2022, 18:00
Document name Document type Date of publishing
Annexes to the contract Jan 4, 2023, 12:59
Electronic signature Jan 4, 2023, 13:02

Change №10

Status:
Confirmed
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
Уточнення порядку фінансування робіт
ID:
0979cf5550c34d2fb21cfe67681bea65
Date:
Oct 24, 2023, 19:54
Number of loaded document:
11
Date of signature:
Oct 23, 2023, 10:00
Document name Document type Date of publishing
Signed contract Oct 24, 2023, 22:53
Electronic signature Oct 24, 2023, 22:54

Change №11

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Затримки фінансування витрат замовника
ID:
82a2bd0d38af4f32b4c340f5e1a45a70
Date:
Jan 2, 2025, 12:30
Number of loaded document:
12
Date of signature:
Dec 31, 2024, 16:00
Document name Document type Date of publishing
Annexes to the contract Jan 2, 2025, 14:29
Electronic signature Jan 2, 2025, 14:30

Change №12

Status:
Confirmed
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Зменшення обсягів закупівлі у зв’язку з уточненням фактичних обсягів робіт згідно Договору та коригуванням проекту
ID:
ad1fc3188e544dd29b49c7846b3d44d5
Date:
Jun 26, 2025, 09:03
Number of loaded document:
13
Date of signature:
Jun 25, 2025, 12:00
Document name Document type Date of publishing
Electronic signature Jun 26, 2025, 12:01
Annexes to the contract Jun 26, 2025, 12:00
Main contact
Name:
Phone:
E-mail:
Fax:
Information about supplier
Name:
Товариство з обмеженою відповідальністю "Сервіскотломонтаж-Львів"
EDRPOU code:
37801512
Website:
Not indicated
Address:
Україна, 79044, Львівська область, Львів, Природна,5б/20
Information about customer
Name:
Середня загальноосвітня школа №72
EDRPOU code:
20781471
Website:
Not indicated
Address:
Україна, 79066, Львівська область, Львів, вул.Зубрівська,1