Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Публікація у відповідності до положень ст. 3 та ст. 10 Закону України "Про публічні закупівлі". Зміна реквізитів через IBAN.
ID:
4ce91ed2adf54cd4a5bc8a6be12839e2
Date:
Nov 6, 2019, 10:51
Number of loaded document:
1
Date of signature:
Nov 4, 2019, 10:47
|
|
Annexes to the contract
|
Nov 6, 2019, 10:51
|
|
|
Electronic signature
|
Nov 6, 2019, 10:51
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
змінено п.п. 2.1, 9.1, 10 Договору
ID:
6e4e514974854255b68d17bc9cf0f6ac
Date:
Dec 26, 2022, 12:55
Number of loaded document:
3
Date of signature:
May 12, 2020, 12:50
|
|
Electronic signature
|
Dec 26, 2022, 12:55
|
|
|
Not indicated
|
Dec 26, 2022, 12:53
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
змінено п.п. 2.1., 9.1 Договору
ID:
94d06dc77498487b819df5d679088fd1
Date:
Dec 26, 2022, 13:01
Number of loaded document:
4
Date of signature:
Sep 1, 2021, 14:56
|
|
Not indicated
|
Dec 26, 2022, 12:58
|
|
|
Electronic signature
|
Dec 26, 2022, 13:01
|
Change №4
Status:
Change cause:
Change of price per unit of goods by no more than 10% in case of price fluctuation of such goods on the market, provided that such change does not lead to an increase in the amount specified in the contract
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
змінено п. 3.1
ID:
24ab1b31f4614af4b27fd5be174a9a48
Date:
Dec 26, 2022, 13:08
Number of loaded document:
5
Date of signature:
Dec 9, 2021, 13:46
|
|
Electronic signature
|
Dec 26, 2022, 13:08
|
|
|
Not indicated
|
Dec 26, 2022, 13:04
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Зміни до п. 9.1 Договору
ID:
0bd4eec67fd743d9a752e8b9572382a8
Date:
Dec 26, 2022, 17:28
Number of loaded document:
7
Date of signature:
Dec 23, 2022, 17:26
|
|
Electronic signature
|
Dec 26, 2022, 17:28
|
|
|
Signed contract
|
Dec 26, 2022, 17:27
|
Change №6
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміни до п.2.1 та п.10
ID:
a531c04eb06f4b34a7d0017acf1f74f2
Date:
Dec 26, 2022, 17:33
Number of loaded document:
6
Date of signature:
Dec 26, 2022, 17:31
|
|
Signed contract
|
Dec 26, 2022, 17:32
|
|
|
Electronic signature
|
Dec 26, 2022, 17:33
|
Change №7
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміни до п.10 Договору
ID:
745aab20c11f435bbb92413ce4afb7fd
Date:
Dec 29, 2022, 17:25
Number of loaded document:
8
Date of signature:
Dec 27, 2022, 17:23
|
|
Signed contract
|
Dec 29, 2022, 17:23
|
|
|
Electronic signature
|
Dec 29, 2022, 17:25
|
Change №8
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Зміни до п.9.1 Договору
ID:
60cd9e145b154b669daaa05f5b1884bd
Date:
Mar 29, 2023, 18:37
Number of loaded document:
9
Date of signature:
Mar 29, 2023, 18:34
|
|
Signed contract
|
Mar 29, 2023, 18:35
|
|
|
Electronic signature
|
Mar 29, 2023, 18:37
|
Change №9
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
змінено п. 9.1 Договору
ID:
dcb2f2772f414fe3b65307503b33482f
Date:
Jun 29, 2023, 14:31
Number of loaded document:
10
Date of signature:
Jun 29, 2023, 14:28
|
|
Electronic signature
|
Jun 29, 2023, 14:31
|
|
|
Not indicated
|
Jun 29, 2023, 14:29
|
Change №10
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
змінено п.2.1
ID:
8424b587271342ad9d02ec433009a26f
Date:
Jul 25, 2023, 12:11
Number of loaded document:
11
Date of signature:
Jul 24, 2023, 14:00
|
|