Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Відповідно до п.1.6. та п.16.9. Договору
ID:
b24b2000f87846129c04025e665aff0b
Date:
Sep 23, 2020, 10:07
Number of loaded document:
1
Date of signature:
Sep 23, 2020, 00:00
|
|
Electronic signature
|
Sep 23, 2020, 10:07
|
|
|
Not indicated
|
Sep 23, 2020, 10:07
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно абз.2 п.3.6 Договору, у зв’язку із затримкою фінансування витрат Замовника
ID:
f2f3a3982d9c4c749be44c733d3f8d9c
Date:
Apr 28, 2021, 10:35
Number of loaded document:
5
Date of signature:
Apr 28, 2021, 00:00
|
|
Electronic signature
|
Apr 28, 2021, 10:34
|
|
|
Not indicated
|
Apr 28, 2021, 10:34
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Згідно п.2.6.3, абз.2 п.3.6 Договору, п.4 ч.5 ст. 41 Закону України "Про публічні закупівлі", у зв’язку із затримкою фінансування витрат Замовника Сторони дійшли згоди подовжити строк виконання робіт
ID:
afec99ad7e63492cb1978fe3e94e2d2a
Date:
May 21, 2021, 08:19
Number of loaded document:
6
Date of signature:
May 21, 2021, 00:00
|
|
Electronic signature
|
May 21, 2021, 08:19
|
|
|
Not indicated
|
May 21, 2021, 08:15
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно п.3.5, п.2.6.3 Договору, п.4 ч.5 ст. 41 Закону України "Про публічні закупівлі", у зв’язку із виникненням обставин, що не залежать від Підрядника і перешкоджають виконанню робіт у встановлені строки Сторони дійшли згоди подовжити строк виконання робіт та викласти п.3.1 Договору в наступній редакції: "3.1. Роботи виконуються по 30 вересня 2021 року, відповідно Календарного графіку виконання робіт."
ID:
856e914e22884b7db254dccfab7a296c
Date:
Aug 2, 2021, 12:03
Number of loaded document:
8
Date of signature:
Jul 30, 2021, 00:00
|
|
Electronic signature
|
Aug 2, 2021, 12:03
|
|
|
Not indicated
|
Aug 2, 2021, 12:03
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Згідно п.3.5, п.2.6.3 Договору, п.4 ч.5 ст. 41 Закону України "Про публічні закупівлі", у зв’язку із виникненням обставин, що не залежать від Підрядника і перешкоджають виконанню робіт у встановлені строки Сторони дійшли згоди подовжити строк виконання робіт.
ID:
8ce23fb5c9834b03b567ec46832345a6
Date:
Nov 2, 2021, 09:20
Number of loaded document:
9
Date of signature:
Oct 29, 2021, 00:00
|
|
Signed contract
|
Nov 2, 2021, 09:20
|
|
|
Electronic signature
|
Nov 2, 2021, 09:20
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із затримкою фінансування витрат замовника, відповідно п.2.6.3, п.12.2 Договору та керуючись п.4 ч.5 ст.41 Закону України "Про публічні закупівлі"
ID:
38871df754b045fc9b1b512621deafc8
Date:
Dec 22, 2021, 13:43
Number of loaded document:
10
Date of signature:
Dec 22, 2021, 00:00
|
|
Signed contract
|
Dec 22, 2021, 13:42
|
|
|
Electronic signature
|
Dec 22, 2021, 13:43
|
Change №7
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв'язку із настанням обставин непереборної сили, що засвідчуються листом Торгово-промислової палати України від 28.02.2022р. № 2024/02.0-7.1 та відповідно п.2.6.3, абз.1 п.3.6 Договору та керуючись п.4 ч.5 ст.41 Закону України "Про публічні закупівлі" Сторони дійшли згоди подовжити строк виконання робіт до 31.12.2022р.
ID:
bb2d083dc15f4a3db424ffba44a5e2f3
Date:
Mar 31, 2022, 14:20
Number of loaded document:
12
Date of signature:
Mar 31, 2022, 00:00
|
|
Signed contract
|
Mar 31, 2022, 14:20
|
|
|
Electronic signature
|
Mar 31, 2022, 14:20
|
Change №8
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У зв’язку із затримкою фінансування витрат замовника, відповідно п.2.6.3, п.12.2 Договору та керуючись п.4 ч.5 ст.41 Закону України "Про публічні закупівлі"
ID:
cb34f073492d4c1a8de1b13fc376e337
Date:
Dec 22, 2022, 16:03
Number of loaded document:
14
Date of signature:
Dec 22, 2022, 00:00
|
|
Electronic signature
|
Dec 22, 2022, 16:03
|
|
|
Signed contract
|
Dec 22, 2022, 16:03
|
Change №9
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Відповідно п.2.6.4 Договору та керуючись п.5 ч.5 ст.41 Закону України "Про публічні закупівлі"- погодження зміни ціни в договорі про закупівлю в бік зменшення (без зміни обсягу та якості робіт)
ID:
292aa8eaebde41c68318c123191a3a54
Date:
Dec 27, 2023, 12:41
Number of loaded document:
16
Date of signature:
Dec 27, 2023, 00:00
|
|
Electronic signature
|
Dec 27, 2023, 14:41
|
|
|
Annexes to the contract
|
Dec 27, 2023, 14:41
|