Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Коригування графіку виконання робіт та плану фінансування (без зміни кінцевого строку виконання робіт)
ID:
d047da4a2a1948138f017601bec6d82c
Date:
Dec 26, 2019, 16:57
Number of loaded document:
1
Date of signature:
Dec 26, 2019, 00:00
|
|
Annexes to the contract
|
Dec 26, 2019, 16:57
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зміна Сторони договору у зв'язку з правонаступництвом
ID:
6e2602588d2d45f484e936465231b46e
Date:
Apr 3, 2020, 16:59
Number of loaded document:
2
Date of signature:
Apr 3, 2020, 00:00
|
|
Annexes to the contract
|
Apr 3, 2020, 16:59
|
Change №3
Status:
Change cause:
Change of conditions due to extension of the contract term, sufficient for conducting procurement procedure at the beginning of the next year, in the amount not exceeding 20% of the amount specified in the contract made in the previous year, if expenses for these purposes are approved in the established order
Note:
Фінансування на 2021 рік
ID:
3199996717cc40e8a23e991f6f828174
Date:
Dec 30, 2020, 13:17
Number of loaded document:
3
Date of signature:
Dec 30, 2020, 00:00
|
|
Annexes to the contract
|
Dec 30, 2020, 13:17
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
зміна фінансування у 2021 році
ID:
414f5461bae74618b697bf325a6e285c
Date:
Apr 26, 2021, 16:48
Number of loaded document:
4
Date of signature:
Apr 22, 2021, 00:00
|
|
Annexes to the contract
|
Apr 26, 2021, 16:48
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
зміна фінансування
ID:
c6d381b169624a56ae624ffeeab9a483
Date:
May 11, 2021, 14:39
Number of loaded document:
4
Date of signature:
Apr 22, 2021, 00:00
|
|
Schedule and stages
|
May 11, 2021, 14:38
|
|
|
Schedule and stages
|
May 11, 2021, 14:38
|
Change №6
Status:
Change cause:
Change of the consumer price index established by state statistics bodies in accordance with legislation, change of foreign currency exchange rate, change of exchange quotations or Platts indicators, regulated prices (tariffs) and norms applied in the procurement contract, in case of establishing the procedure for changing the price in the procurement contract
Note:
збільшення фінансування на роботи у 2021році
ID:
385c217380494e11b00533bdb9811e28
Date:
Jul 5, 2021, 12:14
Number of loaded document:
5
Date of signature:
Jul 5, 2021, 00:00
|
|
Annexes to the contract
|
Jul 5, 2021, 12:14
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Збільшення фінансування, згідно виконаних робіт
ID:
996f9c5e77ab48328b79d3e9773c4963
Date:
Dec 14, 2021, 10:08
Number of loaded document:
6
Date of signature:
Dec 14, 2021, 00:00
|
|
Schedule and stages
|
Dec 14, 2021, 10:07
|
|
|
Annexes to the contract
|
Dec 14, 2021, 10:07
|
|
|
Schedule and stages
|
Dec 14, 2021, 10:08
|
Information about supplier
Name:
ТОВ "ДІЛАЙН ІНЖИНІРИНГ"
EDRPOU code:
38732471
Website:
Not indicated
Address:
Україна, 69063, Запорізька область, місто Запоріжжя, ВУЛИЦЯ СВЯТОГО МИКОЛАЯ / ПОКРОВСЬКА, будинок 29/11
Information about customer
Name:
Інженерненська сільська рада Пологівського району Запорізької області
EDRPOU code:
04353959
Website:
Address:
Україна, 70635, Запорізька область, село Інженерне, вулиця Шевченка,43б, село Інженерне,Пологівський район