Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесено зміни до Додатку 2 та 3 Договору
ID:
5519f618692a44a89719a6fd183f82de
Date:
Nov 26, 2020, 16:14
Number of loaded document:
Додаткова угода №1 до Договору №БДР-167/10-20 від 02.10.2020
Date of signature:
Nov 26, 2020, 16:00
|
|
Electronic signature
|
Nov 26, 2020, 16:14
|
|
|
Annexes to the contract
|
Nov 26, 2020, 16:14
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесено зміни до п. 2.1. Договору
ID:
e24aa4b979a8437daed9ce59775ba43e
Date:
Dec 22, 2020, 16:15
Number of loaded document:
Додаткова угода №2 до Договору №БДР-167/10-20 від 02.10.2020
Date of signature:
Dec 21, 2020, 17:00
|
|
Electronic signature
|
Dec 22, 2020, 16:15
|
|
|
Annexes to the contract
|
Dec 22, 2020, 16:14
|
Change №3
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Внесено зміни до п. 3.1., Додатку 1 та 3 Договору
ID:
2053ae744b4647768f81e8f81333b028
Date:
Dec 24, 2020, 17:32
Number of loaded document:
Додаткова угода №3 до Договору №БДР-167/10-20 від 02.10.2020
Date of signature:
Dec 24, 2020, 17:00
|
|
Annexes to the contract
|
Dec 24, 2020, 17:31
|
|
|
Electronic signature
|
Dec 24, 2020, 17:32
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесено зміни до Додатку 2 Договору
ID:
02a6b57ce80444f889307820041538f6
Date:
Dec 26, 2020, 16:54
Number of loaded document:
Додаткова угода №4 до Договору №БДР-167/10-20 від 02.10.2020
Date of signature:
Dec 24, 2020, 17:05
|
|
Electronic signature
|
Dec 26, 2020, 16:54
|
|
|
Annexes to the contract
|
Dec 26, 2020, 16:54
|
Change №5
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Внесено зміни до п. 3.1., Додатку 1 та 3 Договору
ID:
303449192b604c27b58ac4c80d0825dd
Date:
Dec 30, 2020, 20:27
Number of loaded document:
Додаткова угода №5 до Договору №БДР-167/10-20 від 02.10.2020
Date of signature:
Dec 28, 2020, 17:00
|
|
Annexes to the contract
|
Dec 30, 2020, 20:25
|
|
|
Electronic signature
|
Dec 30, 2020, 20:27
|
Information about supplier
Name:
ТОВАРИСТВО З ОБМЕЖЕНОЮ ВІДПОВІДАЛЬНІСТЮ "МІЖНАРОДНІ ІНЖЕНЕРНІ СИСТЕМИ"
EDRPOU code:
41453894
Website:
Not indicated
Address:
Україна, 46018, Тернопільська обл., місто Тернопіль, ВУЛИЦЯ ВИННИЧЕНКА, будинок 7, квартира 25
Information about customer
Name:
Державне підприємство "Фінансування інфраструктурних проектів"
EDRPOU code:
37264503
Website:
Not indicated
Address:
Україна, 03118, м. Київ, м. Київ, вул. Хотівська, буд. 4-А