Коригування РП школи №5 на 520 місць по вул. Вокзальній в м. Носівка
Valid:
Nov 28, 2016 – Dec 31, 2019
Contract ID :
UA-2016-09-26-000440-b-c2
Number:
82
Date of signature:
Nov 28, 2016, 00:00
Items list
Name | Quantity | Delivery period | Place of delivery |
---|---|---|---|
Name: Коригування РП школи №5 на 520 місць по вул. Вокзальній в м. Носівка
Code DK 021:2015:
45200000-9 Роботи, пов’язані з об’єктами завершеного чи незавершеного будівництва та об’єктів цивільного будівництва
Code:
000 Не визначено
|
Quantity: 1 роб |
Delivery period: Dec 31, 2017, 16:00 |
Place of delivery: Україна, 17105, Чернігівська область, м. Носівка, вул. Вокзальна, 115 |
Procurement documents
Document name | Document type | Date of publishing |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Signed contract | Nov 29, 2016, 12:17 | |
Not indicated | Oct 4, 2018, 17:00 | |
Not indicated | Oct 4, 2018, 16:00 | |
Not indicated | Mar 14, 2018, 10:36 | |
Not indicated | Dec 27, 2017, 18:31 | |
Not indicated | Dec 6, 2017, 12:26 | |
Not indicated | Sep 27, 2017, 12:46 | |
Not indicated | Nov 29, 2016, 12:17 | |
|
||
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Signed contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 | |
Annexes to the contract | Nov 29, 2016, 12:17 |
Changes to contract
Change №1
Status:
Confirmed
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Продовження фінансування робіт по об'єкту
ID:
5fdf0e2110bf4ac3afe7f77c2d7da7d3
Date:
Sep 27, 2017, 12:45
Number of loaded document:
82
Date of signature:
Sep 27, 2017, 12:45
Change №2
Status:
Confirmed
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Збільшення фінансування у 2017 році
ID:
266ac2cfd6b448559b72c32f481a7159
Date:
Dec 6, 2017, 12:24
Number of loaded document:
82
Date of signature:
Dec 6, 2017, 00:00
Document name | Document type | Date of publishing |
Annexes to the contract | Dec 6, 2017, 12:24 | |
Annexes to the contract | Dec 6, 2017, 12:24 | |
Signed contract | Dec 6, 2017, 12:24 |
Change №3
Status:
Confirmed
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Уточнення договірної ціни на 2017 рік
ID:
4d2b4b8c1b564a8c8b1cf3a988143f3f
Date:
Dec 27, 2017, 18:30
Number of loaded document:
82
Date of signature:
Dec 26, 2017, 00:00
Change №4
Status:
Confirmed
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Продовження фінансування робіт
ID:
91aa0303c3d74ae3b81ebf04fb155dcc
Date:
Mar 14, 2018, 10:20
Number of loaded document:
82
Date of signature:
Mar 13, 2018, 00:00
Change №5
Status:
Confirmed
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Продовження фінансування робіт
ID:
73397e926e824267999c4b38149067d9
Date:
Mar 14, 2018, 10:32
Number of loaded document:
82
Date of signature:
Mar 13, 2018, 00:00
Document name | Document type | Date of publishing |
Signed contract | Mar 14, 2018, 10:32 | |
Annexes to the contract | Mar 14, 2018, 10:32 |
Change №6
Status:
Confirmed
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Розірвання договору
ID:
dcb52428cfcc4f70a70de140e9ba552a
Date:
Oct 4, 2018, 15:56
Number of loaded document:
82
Date of signature:
Oct 4, 2018, 00:00
Main contact
Name:
Артеменко Ірина Анатоліївна
Phone:
+380462240284
E-mail:
ukb_zakupivli@ukr.net
Fax:
+380462240054
Information about supplier
Name:
ПП "БУД-АРВЕСТ"
EDRPOU code:
35385371
Web site:
Not indicated
Address:
Україна, 14017, Чернігівська область, Чернігів, вулиця Щорса, будинок 37-Б
Information about customer
Name:
Управління капітального будівництва Чернігівської обласної державної адміністрації
EDRPOU code:
04014246
Web site:
Not indicated
Address:
Україна, 14000, Чернігівська область, місто Чернігів, вулиця Єлецька, 11