Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Уточнення календарного графіку виконання робіт та плану фінансування будівництва
ID:
936763c284584988a0950e46f4705a28
Date:
Oct 31, 2020, 09:59
Number of loaded document:
38_1
Date of signature:
Oct 28, 2020, 00:00
|
|
Signed contract
|
Oct 31, 2020, 09:59
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Уточнення календарного графіку виконання робіт
ID:
be3f77e52eaa4fb2bd81a59d3ff91436
Date:
Dec 16, 2020, 12:29
Number of loaded document:
2
Date of signature:
Dec 15, 2020, 00:00
|
|
Signed contract
|
Dec 16, 2020, 12:29
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та уточнення вартості робіт у 2020 році
ID:
28ad56024d42491abd7e7ba57d60212a
Date:
Dec 23, 2020, 19:31
Number of loaded document:
3
Date of signature:
Dec 21, 2020, 00:00
|
|
Annexes to the contract
|
Dec 23, 2020, 19:31
|
|
|
Signed contract
|
Dec 23, 2020, 19:31
|
|
|
Annexes to the contract
|
Dec 23, 2020, 19:31
|
Change №4
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору та уточнення вартості робіт у 2021 році
ID:
6084adc1602349698e4e11aa225b0572
Date:
Apr 29, 2021, 12:16
Number of loaded document:
4
Date of signature:
Apr 29, 2021, 00:00
|
|
Annexes to the contract
|
Apr 29, 2021, 12:16
|
|
|
Signed contract
|
Apr 29, 2021, 12:16
|
|
|
Annexes to the contract
|
Apr 29, 2021, 12:16
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору, уточнення календарного графіку виконання робіт та плану фінансування будівництва
ID:
d547de3bb93046cc9a17f770f1e84e02
Date:
Jul 2, 2021, 14:07
Number of loaded document:
5
Date of signature:
Jun 30, 2021, 00:00
|
|
Signed contract
|
Jul 2, 2021, 14:07
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії договору, уточнення календарного графіку виконання робіт та плану фінансування будівництва
ID:
6efabd513618425db4779a35d526d6f6
Date:
Aug 18, 2021, 16:40
Number of loaded document:
6
Date of signature:
Aug 13, 2021, 00:00
|
|
Signed contract
|
Aug 18, 2021, 16:39
|
Change №7
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження терміну дії Договору
ID:
fab27a6731fd451597a549dc0ded2b00
Date:
Oct 5, 2021, 16:05
Number of loaded document:
7
Date of signature:
Sep 30, 2021, 00:00
|
|
Signed contract
|
Oct 5, 2021, 16:04
|
Change №8
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Зменшення ціни договору
ID:
2dad1e18dfbc4eb08859b7e41d533941
Date:
Oct 19, 2021, 10:03
Number of loaded document:
8
Date of signature:
Oct 13, 2021, 00:00
|
|
Annexes to the contract
|
Oct 19, 2021, 10:03
|
|
|
Signed contract
|
Oct 19, 2021, 10:03
|
|
|
Annexes to the contract
|
Oct 19, 2021, 10:03
|
|
|
Annexes to the contract
|
Oct 19, 2021, 10:03
|
Information about customer
Name:
Управління капітального будівництва Чернігівської обласної державної адміністрації
EDRPOU code:
04014246
Website:
Not indicated
Address:
Україна, 14000, Чернігівська область, місто Чернігів, вулиця Єлецька, 11