Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони домовилися доповнити Генеральний договір Додатком №3 - "План фінансування робіт"
ID:
3d77cbb9c5e9422bbddd153293f94b0d
Date:
Oct 18, 2021, 16:32
Number of loaded document:
1
Date of signature:
Oct 18, 2021, 16:00
|
|
Signed contract
|
Oct 18, 2021, 16:32
|
|
|
Electronic signature
|
Oct 18, 2021, 16:32
|
Change №2
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони погодились збільшити фінансування робіт на 2021 рік на суму 1551559,20 грн. з ПДВ та відповідно внесли зміни до графіку фінансування по роках та графіку виконання робіт
ID:
3f2f9c3fe6724a8daa79a809a9a032e5
Date:
Dec 14, 2021, 15:00
Number of loaded document:
2
Date of signature:
Dec 14, 2021, 14:00
|
|
Electronic signature
|
Dec 14, 2021, 15:00
|
|
|
Signed contract
|
Dec 14, 2021, 15:00
|
Change №3
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони погодилися внести зміни до Генерального договору в частині порядку розрахунків по роках та внесли відповідні зміни в лпан графік виконання та фінансування робіт по роках. Фінансування робіт на 2022 рік становитиме 294777,60 грн. з ПДВ
ID:
f70361ecc2ff42b09a10933242899bd0
Date:
May 24, 2022, 11:24
Number of loaded document:
3
Date of signature:
May 24, 2022, 10:00
|
|
Signed contract
|
May 24, 2022, 11:23
|
|
|
Electronic signature
|
May 24, 2022, 11:24
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони погодилися внести зміни в п.4.1 Розділу 4 "Вартість робіт та порядок розрахунків" Генерального договору в частині порядку розрахунків по роках та внесли відповідні зміни в календарний графік виконання робіт та план фінансування робіт по роках. Фінансування робіт на 2022 рік становитиме 4000 000,00 грн. з ПДВ, на 2023 рік - 37 890 564,80 грн. з ПДВ, на 2024 рік 19 393 723,20 грн. з ПДВ.
ID:
194e7dfab43242c2b4a75f0393a65567
Date:
Aug 25, 2022, 10:31
Number of loaded document:
№4
Date of signature:
Aug 25, 2022, 10:08
|
|
Electronic signature
|
Aug 25, 2022, 10:31
|
|
|
Not indicated
|
Aug 25, 2022, 10:22
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони погодилися внести зміни щодо фінансування робіт по роках згідно календарного графіку виконання робіт та плану фінансування робіт.
ID:
dd72d017f0a0457ba54040342f46f528
Date:
Sep 19, 2022, 16:34
Number of loaded document:
5
Date of signature:
Sep 19, 2022, 16:00
|
|
Signed contract
|
Sep 19, 2022, 16:33
|
|
|
Electronic signature
|
Sep 19, 2022, 16:34
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторони домовилися перенести подальше виконання робіт на 2023 рік і перенести суму фінансування 2703214,80 грн. на 2023 рік у зв'язку з чим внести зміни щодо фінансування робіт по роках згідно календарного графіку виконання робіт та плану фінансування робіт.
ID:
0172bb62d4eb41dda16e3ebdb521ffb6
Date:
Dec 21, 2022, 16:02
Number of loaded document:
№6
Date of signature:
Dec 21, 2022, 15:58
|
|
Electronic signature
|
Dec 21, 2022, 16:02
|
|
|
Not indicated
|
Dec 21, 2022, 16:00
|