Changes to contract
Change №1
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Змінено обсяги фінансування на 2024-2025 роки
ID:
b9dbc24728764ef3b692f3292805d556
Date:
Aug 23, 2024, 11:16
Number of loaded document:
1
Date of signature:
Aug 22, 2024, 00:00
|
|
Annexes to the contract
|
Aug 23, 2024, 14:16
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Змінено суми фінансування на 2024 та 2025 роки
ID:
d93a2b0445764282b6b3a252926971c5
Date:
Nov 27, 2024, 13:18
Number of loaded document:
2
Date of signature:
Nov 27, 2024, 00:00
|
|
Annexes to the contract
|
Nov 27, 2024, 15:17
|
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
У зв`язку із зміною фінансування витрат Замовника відповідно Рішення БМР БР КО від 13.12.2024 року №1884-83-08 внесені зміни в суми фінансування на 2024-2025 роки.
ID:
4831cf4c1c7244cbba9b3bbf42d15701
Date:
Dec 17, 2024, 13:27
Number of loaded document:
3
Date of signature:
Dec 16, 2024, 00:00
|
|
Annexes to the contract
|
Dec 17, 2024, 15:27
|
Change №4
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Сторонами за взаємною згодою та у зв`язку із затримкою фінансування витрат замовника продовжено строк дії договору без збільшення суми, визначеної в договорі про закупівлю
ID:
ceea9e7506ca4e81a68a612460e22148
Date:
Mar 17, 2025, 11:22
Number of loaded document:
№4
Date of signature:
Mar 17, 2025, 00:00
|
|
Annexes to the contract
|
Mar 17, 2025, 11:22
|
Change №5
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
У зв`язку з уточненням фактично виконаних обсягів будівельних робіт, відповідно зменшена сума Договору на здійснення авторського нагляду
ID:
01957853867741a7966bc4e45c0d29dd
Date:
Nov 26, 2025, 15:19
Number of loaded document:
5
Date of signature:
Nov 25, 2025, 00:00
|
|
Annexes to the contract
|
Nov 26, 2025, 15:19
|
Information about supplier
Name:
Товариство з обмеженою відповідальністю "Науково-виробнича фірма "Мостопроект"
EDRPOU code:
30604691
Website:
Not indicated
Address:
Україна, 04208, Київська область, м. Київ, пр-т. Георгія Гонгадзе,7 к. 33
Information about customer
Name:
Управління будівництва, житлово - комунального господарства, інфраструктури та транспорту Броварської міської ради Броварського району Київської області
EDRPOU code:
26146617
Website:
Not indicated
Address:
Україна, 07400, Київська область, місто Бровари, вул. Героїв України, 15