Changes to contract
Change №1
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Продовження строку дії договору до 31.12.2019
ID:
0504c199c2ea4eae82d3e88ff2abbf46
Date:
Dec 29, 2018, 16:08
Number of loaded document:
Додаткова угода №1 від 26.12.2018 до договору № 118кб від 10.09.2018
Date of signature:
Dec 26, 2018, 09:59
|
|
Electronic signature
|
Dec 29, 2018, 16:08
|
|
|
Annexes to the contract
|
Dec 29, 2018, 09:59
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Публікація у відповідності до положень ст. 3 та ст. 10 Закону України "Про публічні закупівлі"
ID:
c9d5b1978fd448909b9db48607e53a9c
Date:
Mar 22, 2019, 14:28
Number of loaded document:
Додаткова угода № 2 від 21.03.2019 до договору № 118 кб від 10.09.2018
Date of signature:
Mar 21, 2019, 10:18
|
|
Annexes to the contract
|
Mar 22, 2019, 10:18
|
|
|
Electronic signature
|
Mar 22, 2019, 14:28
|
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Публікація у відповідності до положень ст. 3 та ст. 10 Закону України "Про публічні закупівлі". Зміна реквізитів.
ID:
72f4229121564bdf90d169a67cc91729
Date:
Jun 24, 2019, 14:46
Number of loaded document:
Додаткова угода № 3 від 24.06.2019 до договору № 118 кб від 10.09.2018
Date of signature:
Jun 24, 2019, 10:40
|
|
Annexes to the contract
|
Jun 24, 2019, 10:41
|
|
|
Electronic signature
|
Jun 24, 2019, 14:46
|
Change №4
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Публікація у відповідності до положень ст. 3 та ст. 10 Закону України "Про публічні закупівлі". Зміна реквізитів через IBAN
Уточнення обсягів робіт в сторону зменшення: з демонтажу дверних коробок та полотен, улаштування покриття з керамічної плитки, встановлення жалюзійних грат та вентиляційних зонтів, з встановлення силового обладнання. Зміна кошторисних норм.
ID:
e51540a2ec144c7ea78d2afa9c54ada9
Date:
Nov 4, 2019, 17:20
Number of loaded document:
4
Date of signature:
Nov 1, 2019, 17:11
|
|
Electronic signature
|
Nov 4, 2019, 17:20
|
|
|
Annexes to the contract
|
Nov 4, 2019, 17:15
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
У відповідності до п.10.3 договору подовжено строк дії договору до 31.12.2020
ID:
c322c47474674999aa2b416e2ce15e7c
Date:
Dec 26, 2019, 16:00
Number of loaded document:
5
Date of signature:
Dec 26, 2019, 15:57
|
|
Annexes to the contract
|
Dec 26, 2019, 15:58
|
|
|
Electronic signature
|
Dec 26, 2019, 16:00
|
Change №6
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Публікація у відповідності до положень ст.3 та ст.10 Закону України "Про публічні закупівлі". Зміна обсягів фінансування по роках та відповідного плану, зміна р/р Замовника.
ID:
e5baa5cb9b8f4f85892164673b871bf1
Date:
Apr 10, 2020, 16:40
Number of loaded document:
6
Date of signature:
Apr 9, 2020, 16:38
|
|
Annexes to the contract
|
Apr 10, 2020, 16:39
|
|
|
Electronic signature
|
Apr 10, 2020, 16:40
|
Change №7
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
Через зменшення обсягів закупівлі робіт, зменшення ДЦ до 2685462,63 грн. у т. ч. ПДВ 447577,11 грн. Зміна обсягів фінансування по роках та відповідного плану.
ID:
d7202a7c47b74e98b3ab927b57996e04
Date:
Apr 24, 2020, 11:24
Number of loaded document:
7
Date of signature:
Apr 23, 2020, 11:05
|
|
Annexes to the contract
|
Apr 24, 2020, 11:21
|
|
|
Electronic signature
|
Apr 24, 2020, 11:24
|
Information about supplier
Name:
ПРИВАТНЕ ПІДПРИЄМСТВО "ДОНБАС БУДІНДУСТРІЯ СЕРВІС"
EDRPOU code:
33991075
Website:
Not indicated
Address:
Україна, 85322, Донецька область, місто Мирноград, ВУЛИЦЯ ВАТУТІНА будинок 28
Information about customer
Name:
ДЕПАРТАМЕНТ КАПІТАЛЬНОГО БУДІВНИЦТВА ДОНЕЦЬКОЇ ОБЛАСНОЇ ДЕРЖАВНОЇ АДМІНІСТРАЦІЇ
EDRPOU code:
26503980
Website:
Not indicated
Address:
Україна, 84122, Донецька область, м. Слов’янськ, вул. Ярослава Мудрого, 9