ДСТУ Б.Д.1.1-1:2013 Енергоблок №2. Коригування проекту ЮАТ-421-78-РК.ПЗ. РК СГО і вентсистем. ПКД

Valid:
Jun 30, 2022
Contract ID :
UA-2019-08-30-000780-a-a1
Number:
19-123-08-19-05727
Date of signature:
Aug 29, 2019, 00:00

Items list

Name Quantity Delivery period Place of delivery

Name:

ДСТУ Б.Д.1.1-1:2013 Енергоблок №2. Коригування проекту ЮАТ-421-78-РК.ПЗ. РК СГО і вентсистем. ПКД

Code DK 021:2015: 45454000-4 Реконструкція

Quantity:

1 роботи

Delivery period:

Dec 31, 2019, 00:00

Place of delivery:

Україна, 55000, Миколаївська область, Южноукраїнськ, промзона

Procurement documents

Document name Document type Date of publishing
Electronic signature Aug 30, 2019, 11:29
Electronic signature Aug 30, 2019, 11:29
Signed contract Aug 30, 2019, 11:29
Changes to contract

Change №1

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесення змін в календарний план
ID:
b4cd49b613294cdb9fc4c0ad5377141d
Date:
Nov 18, 2019, 13:03
Number of loaded document:
1
Date of signature:
Nov 15, 2019, 00:00
Document name Document type Date of publishing
Annexes to the contract Nov 18, 2019, 13:01
Electronic signature Nov 18, 2019, 13:02

Change №2

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесення змін в календарний план
ID:
f33b1ee348954af2be0a01b4b11385ff
Date:
Nov 4, 2020, 14:58
Number of loaded document:
2
Date of signature:
Nov 3, 2020, 00:00
Document name Document type Date of publishing
Electronic signature Nov 4, 2020, 14:58
Annexes to the contract Nov 4, 2020, 14:57

Change №3

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Внесення змін в календарний план Продовження терміну дії договору до 30.06.2022
ID:
f917a16ad83248ff8655fd1f5c2f9329
Date:
May 6, 2021, 11:57
Number of loaded document:
№3/19-123-08-19-05727
Date of signature:
May 5, 2021, 00:00
Document name Document type Date of publishing
Electronic signature May 6, 2021, 11:57
Annexes to the contract May 6, 2021, 11:56
Main contact
Name:
Довганюк Ирина Григорьевна
Phone:
380513642286
E-mail:
Fax:
0513642412
Information about supplier
Name:
Акціонерне товариство «Харківський науково-дослідний та проектно-конструкторський інститут «Енергопроект»
EDRPOU code:
14078902
Website:
Address:
Україна, 61003, Харківська область, Харків, пр. Московський, 10/12
Information about customer
Name:
ВП ЮУАЕС ДП НАЕК «Енергоатом»
EDRPOU code:
20915546
Website:
Address:
Україна, 55000, Миколаївська область, Южноукраїнськ, Миколаївської обл., м. Южноукраїнськ