Розподіл електричної енергії
Valid:
Jan 16, 2023 – Dec 31, 2023
Contract ID :
UA-2023-01-17-002816-a-a1
Number:
№ 14
Date of signature:
Jan 16, 2023, 10:21
Items list
| Name | Quantity | Delivery period | Place of delivery |
|---|---|---|---|
|
Name: Розподіл електричної енергії
Code DK 021:2015:
65310000-9 Розподіл електричної енергії
|
Quantity: 212,727 Кіловат-година |
Delivery period: Dec 31, 2023, 00:00 |
Place of delivery: Україна, 26555, Кіровоградська область, смт Побузьке, межа балансової належності електроустановок замовника |
Procurement documents
| Document name | Document type | Date of publishing |
| Not indicated | Jan 17, 2023, 10:27 | |
| Electronic signature | Jan 18, 2024, 10:48 |
Changes to contract
Change №1
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
На дату укладання додаткової угоди бюджетні зобов'язання Замовника збільшуються в межах бюджетних призначень, на 19 391,00 (Дев'ятнадцять тисяч триста дев'яносто одна) грн. 00 коп. з ПДВ.
Всі інші умови Договору залишаються незмінними і Сторони підтверджують по них свої зобов’язання.
ID:
21c87d7b161541cc82dda9c0b2025072
Date:
Jun 22, 2023, 08:33
Number of loaded document:
1
Date of signature:
Jun 21, 2023, 08:31
| Document name | Document type | Date of publishing |
| Electronic signature | Jun 22, 2023, 08:33 | |
| Not indicated | Jun 22, 2023, 08:32 |
Change №2
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
На дату укладання додаткової угоди бюджетні зобов'язання Замовника збільшуються в межах бюджетних призначень, на 2 370,00 з ПДВ. Всі інші умови Договору залишаються незмінними і Сторони підтверджують по них свої зобов’язання.
ID:
5e3b04278fb144e9b592bd27565717e1
Date:
Jul 25, 2023, 15:49
Number of loaded document:
№ 2
Date of signature:
Jul 25, 2023, 15:47
| Document name | Document type | Date of publishing |
| Not indicated | Jul 25, 2023, 15:47 | |
| Electronic signature | Jul 25, 2023, 15:49 |
Change №3
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
На дату укладання додаткової угоди бюджетні
зобов'язання Замовника збільшуються в межах
бюджетних призначень, на 3 630,00 з ПДВ. Всі інші
умови Договору залишаються незмінними і Сторони
підтверджують по них свої зобов’язання.
ID:
7807011907ab4ae689795f04069e930f
Date:
Jul 26, 2023, 16:12
Number of loaded document:
3
Date of signature:
Jul 26, 2023, 16:04
| Document name | Document type | Date of publishing |
| Electronic signature | Jul 26, 2023, 16:12 | |
| Not indicated | Jul 26, 2023, 16:06 |
Change №4
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
На дату укладання додаткової угоди бюджетні зобов'язання Замовника збільшуються в межах бюджетних призначень, на 50 000 (П'ятдесят тисяч) гри. 00 коп. з ПДВ.
ID:
3abcb79919074fee83a00fc524b4ef74
Date:
Aug 18, 2023, 11:52
Number of loaded document:
4
Date of signature:
Aug 18, 2023, 11:39
| Document name | Document type | Date of publishing |
| Electronic signature | Aug 18, 2023, 11:52 | |
| Not indicated | Aug 18, 2023, 11:43 |
Change №5
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
1. На дату укладання додаткової угоди бюджетні зобов'язання Замовника збільшуються в межах бюджетних призначень, на 50 000,00 (П'ятдесят тисяч) грн. 00 коп. з ПДВ.
2. Реквізити Замовника, викласти у новій редакції:
«ЗАМОВНИК: ПОБУЗЬКИЙ ЛІЦЕЙ ПОБУЗЬКОЇ СЕЛИЩНОЇ РАДИ ГОЛОВАНІВСЬКОГО РАЙОНУ КІРОВОГРАДСЬКОЇ ОБЛАСТІ
Адреса: 26555, Кіровоградська обл., Голованівський р-н, смт. Побузьке, вул. Шкільна, 8
Код ЄДРПОУ: 33351162,
р/р: UA378201720344240003000098340;
р/р: UA098201720344260003093098340,
в УКДСУ в Голованівському районі. МФО: 820172,
Телефон: (05252) 5-12-74, E-mail: [email protected]»
ID:
4be7a9860edb4e918578339c57a1f6b1
Date:
Nov 15, 2023, 09:45
Number of loaded document:
5
Date of signature:
Nov 15, 2023, 11:44
| Document name | Document type | Date of publishing |
| Electronic signature | Nov 15, 2023, 11:45 | |
| Not indicated | Nov 15, 2023, 11:44 |
Change №6
Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
На дату укладання додаткової угоди бюджетні зобов'язання Замовника збільшуються в межах бюджетних призначень, на 537,88 (П'ятсот тридцять сім) грн. 88 коп. з ПДВ.
ID:
7ac633c4ed034967a9f575f78c7260c2
Date:
Dec 25, 2023, 09:40
Number of loaded document:
6
Date of signature:
Dec 25, 2023, 11:39
| Document name | Document type | Date of publishing |
| Not indicated | Dec 25, 2023, 11:39 | |
| Electronic signature | Dec 25, 2023, 11:40 |
Main contact
Information about supplier
Name:
ПРИВАТНЕ АКЦІОНЕРНЕ ТОВАРИСТВО "КІРОВОГРАДОБЛЕНЕРГО" ГОЛОВАНІВСЬКИЙ РАЙОН ЕЛЕКТРИЧНИХ МЕРЕЖ
EDRPOU code:
23226362
Website:
Not indicated
Address:
Україна, 26500, Кіровоградська область, смт. Голованівськ, вул. Матросова, 45
Information about customer
Name:
ПОБУЗЬКИЙ ЛІЦЕЙ ПОБУЗЬКОЇ СЕЛИЩНОЇ РАДИ ГОЛОВАНІВСЬКОГО РАЙОНУ КІРОВОГРАДСЬКОЇ ОБЛАСТІ
EDRPOU code:
33351162
Website:
Not indicated
Address:
Україна, 26555, Кіровоградська область, Голованівський район, селище міського типу Побузьке ВУЛИЦЯ ШКІЛЬНА будинок 8