Changes to contract
Change №1
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Уточнення Додатку 4
ID:
bfb84d8943564da181930956554f46cf
Date:
Dec 16, 2019, 12:15
Number of loaded document:
1
Date of signature:
Dec 16, 2019, 12:07
|
Not indicated
|
Dec 16, 2019, 12:15
|
|
Annexes to the contract
|
Dec 16, 2019, 12:15
|
Change №2
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Зміна постанови КМУ щодо авансування та зміна реквізитів
ID:
dead77ad35704a68a4bcf3ce59a27c2b
Date:
Feb 27, 2020, 18:51
Number of loaded document:
2
Date of signature:
Feb 26, 2020, 15:00
|
Annexes to the contract
|
Feb 27, 2020, 18:48
|
|
Not indicated
|
Feb 27, 2020, 18:51
|
Change №3
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Реквізити замовника та календарний графік викладено в новій редакції
ID:
8fd37747d21d47d69ba66bf494616664
Date:
May 5, 2020, 15:43
Number of loaded document:
3
Date of signature:
May 5, 2020, 15:42
|
Not indicated
|
May 5, 2020, 15:43
|
|
Annexes to the contract
|
May 5, 2020, 15:42
|
Change №4
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Пункт 20 договору викладено в новій редакції
ID:
9c911b3fa750462391bbbc76aeea2e36
Date:
Dec 1, 2020, 10:55
Number of loaded document:
4
Date of signature:
Nov 30, 2020, 10:51
|
Not indicated
|
Dec 1, 2020, 10:55
|
|
Annexes to the contract
|
Dec 1, 2020, 10:54
|
Change №5
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Строк дії договору до 30.10.2021р
ID:
96a8ca7adb644ec288680eb1d55dbdfe
Date:
Dec 28, 2020, 13:32
Number of loaded document:
5
Date of signature:
Dec 28, 2020, 13:31
|
Not indicated
|
Dec 28, 2020, 13:32
|
|
Annexes to the contract
|
Dec 28, 2020, 13:32
|
Change №6
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Договір доплвнений пунктом 13.4
ID:
519d17bb34f8400db5b6ef7edec82303
Date:
Mar 22, 2021, 16:20
Number of loaded document:
6
Date of signature:
Mar 22, 2021, 16:13
|
Not indicated
|
Mar 22, 2021, 16:20
|
|
Annexes to the contract
|
Mar 22, 2021, 16:14
|
Change №7
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
У зв'язку з отриманням відкоригованої проєктної документації та нового експертного звіту, договірна ціна викладена в новій редакції
ID:
4a22062ba5c744ff87e80abcd183a48a
Date:
May 5, 2021, 16:00
Number of loaded document:
7
Date of signature:
Apr 30, 2021, 15:57
|
Annexes to the contract
|
May 5, 2021, 15:59
|
|
Not indicated
|
May 5, 2021, 16:00
|
Change №8
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Строк дії договору становить до 01.02.2022р
ID:
a3524aed553149c891ad2c57e29b990c
Date:
May 28, 2021, 10:07
Number of loaded document:
8
Date of signature:
May 26, 2021, 10:06
|
Not indicated
|
May 28, 2021, 10:07
|
|
Annexes to the contract
|
May 28, 2021, 10:06
|
Change №9
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Зміна керівника, реквізити Підрядника викладені в новій редакції
ID:
b21799e936864af5aebd09a2d81e973b
Date:
Jul 20, 2021, 13:54
Number of loaded document:
9
Date of signature:
Jul 19, 2021, 13:53
|
Annexes to the contract
|
Jul 20, 2021, 13:53
|
|
Not indicated
|
Jul 20, 2021, 13:54
|
Change №10
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
План фінансування виконаних робіт викладений в новій редакції
ID:
4cd85100e97c4c5aae0285f76da414af
Date:
Sep 17, 2021, 08:09
Number of loaded document:
10
Date of signature:
Sep 14, 2021, 08:06
|
Not indicated
|
Sep 17, 2021, 08:09
|
|
Annexes to the contract
|
Sep 17, 2021, 08:08
|
Change №11
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
У зв'язку з отриманням відкоригованої проєктної документації та нового експертного звіту, Договірна ціна викладена в новій редакції
ID:
1cc5c56723fa448c8e6ad2adaea2effe
Date:
Sep 17, 2021, 08:14
Number of loaded document:
11
Date of signature:
Sep 14, 2021, 08:10
|
Not indicated
|
Sep 17, 2021, 08:14
|
|
Annexes to the contract
|
Sep 17, 2021, 08:13
|
Change №12
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
План фінансування виконаних робіт викладений в новій редакції
ID:
85f893d5fe0c49e8a49ebdea9d0d65ae
Date:
Sep 27, 2021, 10:21
Number of loaded document:
12
Date of signature:
Sep 27, 2021, 10:20
|
Annexes to the contract
|
Sep 27, 2021, 10:21
|
|
Not indicated
|
Sep 27, 2021, 10:21
|
Change №13
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Строк дії договору до 30.09.2022р
ID:
c9f24fe1d42646e4a263486e39bc51ed
Date:
Nov 1, 2021, 16:40
Number of loaded document:
13
Date of signature:
Nov 1, 2021, 16:40
|
Annexes to the contract
|
Nov 1, 2021, 16:40
|
|
Not indicated
|
Nov 1, 2021, 16:40
|
Change №14
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Пункт 12.1.1 договору викладений в новій редакції
ID:
8561def797654286a5d4d17b7690b204
Date:
Dec 7, 2021, 13:35
Number of loaded document:
14
Date of signature:
Dec 6, 2021, 13:34
|
Annexes to the contract
|
Dec 7, 2021, 13:35
|
|
Not indicated
|
Dec 7, 2021, 13:35
|
Change №15
Status:
Change cause:
Improving the quality of procurement subject, provided that such improvement will not increase contract budget
Note:
Уточнення строків фінансування робіт
ID:
a22f3488b0db4ef6839ac68f423f34cd
Date:
Feb 18, 2022, 09:58
Number of loaded document:
15
Date of signature:
Feb 18, 2022, 09:56
|
Annexes to the contract
|
Feb 18, 2022, 09:57
|
|
Not indicated
|
Feb 18, 2022, 09:58
|
Change №16
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Продовження строку дії договору
ID:
c61a5a78fb4b40788ee1e7f3e557ca63
Date:
Sep 30, 2022, 19:25
Number of loaded document:
16
Date of signature:
Sep 30, 2022, 19:24
|
Annexes to the contract
|
Sep 30, 2022, 19:24
|
|
Not indicated
|
Sep 30, 2022, 19:25
|
Change №17
Status:
Change cause:
Extension of the contract and the fulfillment of obligations under transfer of the goods, works performance, rendering of services in the case of a documented objective circumstances that led to such extension, including force majeure, delays in financing customer expenses, provided that such changes will not increase contract budget.
Note:
Продовження строку дії договору
ID:
077f12de60884dbdb5dc75403d295a58
Date:
Mar 28, 2023, 11:53
Number of loaded document:
17
Date of signature:
Mar 27, 2023, 11:46
|
Not indicated
|
Mar 28, 2023, 11:53
|
|
Not indicated
|
Mar 28, 2023, 11:47
|
|
Annexes to the contract
|
Mar 28, 2023, 11:47
|