Вугілля кам"яне марки ДГ (13-100)

Valid:
Jun 14, 2017 – Dec 31, 2017
Contract ID :
UA-2017-05-11-000133-b-b1
Number:
160
Date of signature:
Jun 14, 2017, 12:00

Items list

Name Quantity Delivery period Place of delivery

Name:

Вугілля кам"яне марки ДГ (13-100)

Code DK 021:2015: 09110000-3 Тверде паливо

Quantity:

350 тонни

Delivery period:

Jun 20, 2017, 23:59 – Jul 30, 2017, 23:59

Place of delivery:

Україна, 16252, Чернігівська область, с.Билка, Загребелля,74

Procurement documents

Document name Document type Date of publishing
Electronic signature Jun 14, 2017, 14:27
Electronic signature Jun 14, 2017, 14:27
Signed contract Jun 14, 2017, 14:23
Changes to contract

Change №1

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Пунк 1.1 Договору викласти в такій редакції "Постачальник зобов"язується до 1 вересня 2017року поставити Замовнику товар зазначений в п.1.2,а Замовник прийняти і оплатити такий товар в асортименті ,кількості та за ціною ,яка зазначена у специфікації(д.1).Пунк 5.1"Строк поставки товару: постачання товару здійснюється протягом 7 к.днів з моменту отримання заявки Постачальником до 1 вересня 2017року"
ID:
be2da3103f3044a282082add0090ca46
Date:
Jul 28, 2017, 15:56
Number of loaded document:
160
Date of signature:
Jul 28, 2017, 11:00
Document name Document type Date of publishing
Electronic signature Jul 28, 2017, 15:56
Annexes to the contract Jul 28, 2017, 15:53

Change №2

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Пункт 5.1 договору про закупівлю товарів за державні кошти №160 від 14.06.17р.викласти у наступній редакції :№Строк поставки товару:постачання товару здійснюється протягом 7к/днів з моменту отримання заявки Постачальником до 01.10.17р."
ID:
7ec5e307365749eb82e5b30f82772e83
Date:
Nov 1, 2017, 16:04
Number of loaded document:
160
Date of signature:
Sep 11, 2017, 15:00
Document name Document type Date of publishing
Electronic signature Nov 1, 2017, 16:04
Annexes to the contract Nov 1, 2017, 15:30

Change №3

Status:
Confirmed
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Пункт5.1 договору про закупівлю товарів за державні кошти №16 від 14.06.2017р.викласти в наступній редакції:"Строк поставки товару: постачання товару здійснюється протягом 7к/днів з моменту отримання заявки Постачальником до 01.12.2017року"
ID:
59bb3487203146b8aed3e16a853bc85f
Date:
Nov 1, 2017, 16:14
Number of loaded document:
160
Date of signature:
Oct 31, 2017, 16:00
Document name Document type Date of publishing
Electronic signature Nov 1, 2017, 16:13
Annexes to the contract Nov 1, 2017, 16:08

Change №4

Status:
Confirmed
Change cause:
Change of conditions due to extension of the contract term, sufficient for conducting procurement procedure at the beginning of the next year, in the amount not exceeding 20% of the amount specified in the contract made in the previous year, if expenses for these purposes are approved in the established order
Note:
Дія Договору продовжується на строк, достатній для проведення процедури закупівлі на початку наступного 2018 року, в обсязі, що не перевищує 20 відсотків суми, визначеної у Договорі» і становить 171400,00 грн. (Сто сімдесят одна тисяча вісімсот чотириста гривень 00 копійок).
ID:
67852a3519784f70991edc1118d8dc93
Date:
Feb 19, 2018, 16:46
Number of loaded document:
160
Date of signature:
Feb 19, 2018, 16:28
Document name Document type Date of publishing
Electronic signature Feb 19, 2018, 16:46
Annexes to the contract Feb 19, 2018, 16:31
Main contact
Name:
Червоненський психоневрологічний інтернат Леденко
Phone:
+380465623788
E-mail:
Fax:
Information about supplier
Name:
ТОВАРИСТВО З ОБМЕЖЕНОЮ ВІДПОВІДАЛЬНІСТЮ "ЧЕРНІГІВЕКОРЕСУРС"
EDRPOU code:
41080763
Website:
Not indicated
Address:
Україна, 14021, Чернігівська обл., місто Чернігів, ВУЛИЦЯ КУРСЬКА, будинок 23
Information about customer
Name:
Червоненський психоневрологічний інтернат
EDRPOU code:
03189877
Website:
Not indicated
Address:
Україна, 16252, Чернігівська область, село Билка Коропський район, вул. Загребелля, 74