Changes to contract
Change №1
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Наявність матеріальних ресурсів поставки Замовника.
ID:
876a0e35de27465a88c6dc890bbe2089
Date:
Oct 27, 2017, 09:40
Number of loaded document:
20/08-2017
Date of signature:
Oct 24, 2017, 16:00
|
|
Electronic signature
|
Oct 27, 2017, 09:40
|
|
|
Annexes to the contract
|
Oct 27, 2017, 09:37
|
Change №2
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Збільшення обсягів робіт у зв`язку з додатковим фінансуванням на 2017 рік.
ID:
f7be2211b7fa49f3b870d21faf248ecd
Date:
Nov 29, 2017, 17:06
Number of loaded document:
20/08-2017
Date of signature:
Nov 28, 2017, 16:00
|
|
Electronic signature
|
Nov 29, 2017, 17:06
|
|
|
Annexes to the contract
|
Nov 29, 2017, 17:05
|
Change №3
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зменшення обсягів фінансування за рахунок коштів бюджету міста Харкова у 2017 році.
ID:
dcbcadaa1d2c4a02b991e92a489990d7
Date:
Dec 21, 2017, 18:05
Number of loaded document:
20/08-2017
Date of signature:
Dec 21, 2017, 18:00
|
|
Electronic signature
|
Dec 21, 2017, 18:05
|
|
|
Annexes to the contract
|
Dec 21, 2017, 18:03
|
Change №4
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Зменшення обсягів фінансування за рахунок коштів бюджету міста Харкова у 2017 році.
ID:
22bc663148954ab48ccc67336234f3e8
Date:
Dec 28, 2017, 15:43
Number of loaded document:
20/08-2017
Date of signature:
Dec 28, 2017, 15:39
|
|
Annexes to the contract
|
Dec 28, 2017, 15:42
|
|
|
Electronic signature
|
Dec 28, 2017, 15:43
|
Change №5
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Наявність матеріальних ресурсів поставки Замовника
ID:
b5daee0462a44564b85d72b59c8388c7
Date:
Jan 26, 2018, 15:38
Number of loaded document:
20/08-2017
Date of signature:
Jan 26, 2018, 15:00
|
|
Annexes to the contract
|
Jan 26, 2018, 15:36
|
|
|
Electronic signature
|
Jan 26, 2018, 15:38
|
Change №6
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Наявність матеріальних ресурсів поставки Замовника.
ID:
9e25af525f8541f28395e491fa2e1ad3
Date:
Jan 30, 2018, 13:59
Number of loaded document:
20/08-2017
Date of signature:
Jan 29, 2018, 17:00
|
|
Electronic signature
|
Jan 30, 2018, 13:59
|
|
|
Annexes to the contract
|
Jan 30, 2018, 13:56
|
Change №7
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Наявність матеріалів поставки Замовника
ID:
b3220bbfd7a14a1c913308a2bd1e0408
Date:
May 21, 2018, 08:53
Number of loaded document:
№20/08-2017
Date of signature:
May 18, 2018, 14:00
|
|
Electronic signature
|
May 21, 2018, 08:53
|
|
|
Annexes to the contract
|
May 21, 2018, 08:48
|
Change №8
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Додаткове фінансування на поточний 2018 рік
ID:
f396f633b41f41bbae75ca442ef2a023
Date:
Sep 6, 2018, 12:02
Number of loaded document:
20/08-2017
Date of signature:
Sep 6, 2018, 11:30
|
|
Not indicated
|
Sep 5, 2018, 08:32
|
|
|
Electronic signature
|
Sep 6, 2018, 12:02
|
|
|
Not indicated
|
Sep 6, 2018, 12:00
|
Change №9
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Визначено в додатковій угоді
ID:
9f695a44961d4cc5ae08edadb263b7bd
Date:
Sep 7, 2018, 13:25
Number of loaded document:
20/08-2017
Date of signature:
Sep 6, 2018, 16:00
|
|
Not indicated
|
Sep 7, 2018, 13:23
|
|
|
Electronic signature
|
Sep 7, 2018, 13:25
|
Change №10
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Виділення додаткових коштів рішенням Харківської міської ради
ID:
ed8248c221594c368effeb533b8ee32c
Date:
Dec 14, 2018, 13:39
Number of loaded document:
20/08-2017
Date of signature:
Dec 12, 2018, 14:00
|
|
Annexes to the contract
|
Dec 14, 2018, 13:33
|
|
|
Electronic signature
|
Dec 14, 2018, 13:39
|
Change №11
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Часткове зменшення фінансування
ID:
55808d3c88a24945a4fed28c4296f757
Date:
Dec 28, 2018, 09:17
Number of loaded document:
20/08-2017
Date of signature:
Dec 27, 2018, 14:00
|
|
Annexes to the contract
|
Dec 28, 2018, 09:17
|
|
|
Electronic signature
|
Dec 28, 2018, 09:17
|
Change №12
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Виділення коштів на 2019 рік відповідно до рішення сесії Харківської міської ради
ID:
f0fccc04daa3469eacacafa865bafa69
Date:
Feb 8, 2019, 15:32
Number of loaded document:
20/08-2017
Date of signature:
Feb 8, 2019, 10:00
|
|
Annexes to the contract
|
Feb 8, 2019, 15:30
|
|
|
Electronic signature
|
Feb 8, 2019, 15:32
|
Change №13
Status:
Change cause:
Reduction of procurement volumes, including taking into account the actual volume of customer's expenses
Note:
П. 1 ч. 4 ст. 36 Закону України «Про публічні закупівлі» (зменшення обсягів закупівлі)
ID:
ae78f30e2e784429a7cbc606847cd5a7
Date:
May 20, 2019, 15:06
Number of loaded document:
20/08-2017
Date of signature:
May 20, 2019, 10:00
|
|
Electronic signature
|
May 20, 2019, 15:06
|
|
|
Annexes to the contract
|
May 20, 2019, 15:04
|
Change №14
Status:
Change cause:
Improvement of the quality of the subject of procurement provided that such improvement will not lead to an increase in the amount specified in the contract
Note:
Покращення якості предмета закупівлі
ID:
8607692ab8fa4729b9312ffd3fb48dd7
Date:
Jun 7, 2019, 11:54
Number of loaded document:
20/08-2017
Date of signature:
Jun 7, 2019, 10:00
|
|
Annexes to the contract
|
Jun 7, 2019, 11:53
|
|
|
Electronic signature
|
Jun 7, 2019, 11:54
|
Change №15
Status:
Change cause:
Extension of the contract term and fulfillment of obligations for transfer of goods, performance of works, provision of services in case of occurrence of documented objectively justified circumstances that caused such extension, including force majeure, delay in financing of customer's expenses, provided that such changes will not lead to an increase in the amount specified in the contract
Note:
Виконання зобов’язань щодо виконання робіт
ID:
507348336cab419ba568a66597daa6c3
Date:
Jun 27, 2019, 14:01
Number of loaded document:
20/08-2017
Date of signature:
Jun 27, 2019, 11:00
|
|
Electronic signature
|
Jun 27, 2019, 14:01
|
|
|
Annexes to the contract
|
Jun 27, 2019, 14:01
|
Change №16
Status:
Change cause:
Agreed price change downwards (without changing the quantity (volume) and quality of goods, works and services)
Note:
Зменшення обсягу закупівлі
ID:
a0bfb3bfdd5642b5a586e8f494220690
Date:
Aug 30, 2019, 13:42
Number of loaded document:
17
Date of signature:
Aug 30, 2019, 11:30
|
|
Annexes to the contract
|
Aug 30, 2019, 13:40
|
|
|
Electronic signature
|
Aug 30, 2019, 13:42
|