Требование
20Т-217_42510000-4 - Теплообмінники, кондиціонери повітря, холодильне обладнання та фільтрувальні пристрої (Комплекс обладнання УПВВ)
требование
to start the bid of equipment after the design work is done
UGV is separated the tender of design from the tender of procurement that as we think is creating a problems. Our understanding is that the UGV will not combine them into one, is that right? If the design and procurement bids are processing in parallel, it would be hard for participants to calculate procurement price without completed unified design package because there might be various design results of the equipment from different design companies, which would affect the equipment procurement price a lot. Therefore, we suggest to arrange it with two steps. First step is to selects one company to do design work first. After design work is done, the step two is to invite the bid of equipment procurement part.
Рассмотрено
Дата подачи:
18 янв. 2021 00:03
Дата изменения:
26 февр. 2021 21:20
Тип:
Требование
ID:
ecdb922314984c9dbf6516c4521e758b
Идентификатор:
UA-2020-12-30-004851-c.a3
Решение заказчика
Дата принятия решения:
20 янв. 2021 14:04
Статус:
отклонено
Оценка автора требования
Решением заказчика удовлетворен
Информация о заказчике
Наименование:
Код ЕГРПОУ:
30019775
Веб сайт:
Адрес:
Україна, 04053, м. Київ, г. Киев, Шевченківський район ВУЛИЦЯ КУДРЯВСЬКА будинок 26/28
Рейтинг: